Topic 15 Practice Test 1 covers Azure Backup and Site Recovery for Microsoft Azure Administrator AZ-104 and maps to the objective: Implement backup and recovery. For broader exam preparation, review the Microsoft AZ-104 Exam Dumps. Every option includes focused technical reasoning explaining both the Azure concept and its fit to the scenario.
Question 1
During an operational review at Woodgrove Bank, the team finds that the environment has three production Azure VMs in West Europe and needs centralized scheduled backups with recovery points managed by Azure Backup. What should the administrator use? Choose ONE.
- Create a Recovery Services vault in the Azure VM region and configure Azure VM backup
- Create a Backup vault and configure Azure Disk Backup
- Create or update an Azure Backup policy with the required schedule and retention
- Enable Azure Site Recovery replication to the secondary region and configure the target resources
Correct Answer: A
Correct Answer
Answer A is correct because Recovery Services vaults manage recovery points and backup operations for supported workloads such as Azure virtual machines. For Azure VM backup, the vault used to protect the workload must be in the same region as the protected data source. For this design, the team must protect Azure virtual machines with the Azure VM backup workflow in the same Azure region as the VMs. That is the best fit here.
Incorrect Answers
Answer B is incorrect because Azure Disk Backup is managed through a Backup vault and uses incremental snapshots in the operational tier. It protects managed disks without requiring the Azure VM backup workflow in a Recovery Services vault. The scenario requires the team to protect Azure virtual machines with the Azure VM backup workflow in the same Azure region as the VMs. This misses the scenario’s key constraint.
Answer C is incorrect because Azure Backup policies control scheduled backup frequency and recovery-point retention so protected workloads follow a consistent recovery policy. The requested outcome is to protect Azure virtual machines with the Azure VM backup workflow in the same Azure region as the VMs. That does not meet the deciding constraint.
Answer D is incorrect because Azure Site Recovery continuously replicates protected workloads to the configured recovery location and orchestrates recovery. Azure-to-Azure disaster recovery requires replication and target-region settings before a regional outage occurs. For this design, the team must protect Azure virtual machines with the Azure VM backup workflow in the same Azure region as the VMs. This solves a different Azure problem.
Question 2
At Lucerne Publishing, the team is onboarding a new Azure VM to backup and needs the supported vault type for VM recovery points. Which option best meets the requirement? Choose ONE.
- Create a Backup vault and configure Azure Disk Backup
- Create a Recovery Services vault in the Azure VM region and configure Azure VM backup
- Create or update an Azure Backup policy with the required schedule and retention
- Enable Azure Site Recovery replication to the secondary region and configure the target resources
Correct Answer: B
Correct Answer
Answer B is correct because Recovery Services vaults manage recovery points and backup operations for supported workloads such as Azure virtual machines. For Azure VM backup, the vault used to protect the workload must be in the same region as the protected data source. Here the administrator must protect Azure virtual machines with the Azure VM backup workflow in the same Azure region as the VMs. This is the required platform behavior.
Incorrect Answers
Answer A is incorrect because Azure Disk Backup is managed through a Backup vault and uses incremental snapshots in the operational tier. It protects managed disks without requiring the Azure VM backup workflow in a Recovery Services vault. The requested outcome is to protect Azure virtual machines with the Azure VM backup workflow in the same Azure region as the VMs. That behavior differs from the requirement.
Answer C is incorrect because For scheduled protection, the backup policy sets when backups run and how long each class of recovery point remains available. The key requirement is to protect Azure virtual machines with the Azure VM backup workflow in the same Azure region as the VMs. This would not produce the requested result.
Answer D is incorrect because Azure Site Recovery continuously replicates protected workloads to the configured recovery location and orchestrates recovery. Azure-to-Azure disaster recovery requires replication and target-region settings before a regional outage occurs. The requirement is to protect Azure virtual machines with the Azure VM backup workflow in the same Azure region as the VMs. That feature addresses another administration need.
Question 3
An Azure administrator for Contoso learns that the environment is choosing the vault type for Azure Disk Backup rather than for whole-VM recovery points. What should be done? Choose ONE.
- Create a Recovery Services vault in the Azure VM region and configure Azure VM backup
- Create or update an Azure Backup policy with the required schedule and retention
- Create a Backup vault and configure Azure Disk Backup
- Run an on-demand backup before the planned change
Correct Answer: C
Correct Answer
Answer C is correct because Azure Disk Backup is managed through a Backup vault and uses incremental snapshots in the operational tier. It protects managed disks without requiring the Azure VM backup workflow in a Recovery Services vault. The deciding need is to protect a managed Azure disk by using the Azure Disk Backup operational-tier snapshot workflow. That directly meets the stated constraint.
Incorrect Answers
Answer A is incorrect because Recovery Services vaults manage recovery points and backup operations for supported workloads such as Azure virtual machines. For Azure VM backup, the vault used to protect the workload must be in the same region as the protected data source. Operationally, the team must protect a managed Azure disk by using the Azure Disk Backup operational-tier snapshot workflow. This solves a different Azure problem.
Answer B is incorrect because Azure Backup policies control scheduled backup frequency and recovery-point retention so protected workloads follow a consistent recovery policy. The requirement is to protect a managed Azure disk by using the Azure Disk Backup operational-tier snapshot workflow. That leaves the required outcome unmet.
Answer D is incorrect because Azure Backup can run an additional backup on demand so administrators have a recent recovery point before an upgrade or configuration change. The scenario requires the team to protect a managed Azure disk by using the Azure Disk Backup operational-tier snapshot workflow. This is adjacent, but not sufficient.
Question 4
At Fourth Coffee, the team must protect a standalone managed data disk with policy-driven incremental snapshots without configuring full Azure VM backup. Which option best meets the requirement? Choose ONE.
- Create a Recovery Services vault in the Azure VM region and configure Azure VM backup
- Create or update an Azure Backup policy with the required schedule and retention
- Run an on-demand backup before the planned change
- Create a Backup vault and configure Azure Disk Backup
Correct Answer: D
Correct Answer
Answer D is correct because Azure Disk Backup is managed through a Backup vault and uses incremental snapshots in the operational tier. It protects managed disks without requiring the Azure VM backup workflow in a Recovery Services vault. Operationally, the team must protect a managed Azure disk by using the Azure Disk Backup operational-tier snapshot workflow. This directly implements the requested outcome.
Incorrect Answers
Answer A is incorrect because Recovery Services vaults manage recovery points and backup operations for supported workloads such as Azure virtual machines. For Azure VM backup, the vault used to protect the workload must be in the same region as the protected data source. For this design, the team must protect a managed Azure disk by using the Azure Disk Backup operational-tier snapshot workflow. That feature addresses another administration need.
Answer B is incorrect because Azure Backup policies control scheduled backup frequency and recovery-point retention so protected workloads follow a consistent recovery policy. The scenario requires the team to protect a managed Azure disk by using the Azure Disk Backup operational-tier snapshot workflow. This misses the scenario’s key constraint.
Answer C is incorrect because An on-demand backup creates an extra recovery point outside the regular schedule, which is useful immediately before a risky maintenance change. The requested outcome is to protect a managed Azure disk by using the Azure Disk Backup operational-tier snapshot workflow. That does not meet the deciding constraint.
Question 5
An Azure administrator for Trey Research learns that the environment must keep daily Azure VM recovery points for 30 days and weekly points for a longer retention period. What should be done? Choose ONE.
- Create or update an Azure Backup policy with the required schedule and retention
- Run an on-demand backup before the planned change
- Create a Recovery Services vault in the Azure VM region and configure Azure VM backup
- Configure vault diagnostic settings to send Azure Backup data to Log Analytics for Backup reports
Correct Answer: A
Correct Answer
Answer A is correct because Azure Backup policies control scheduled backup frequency and recovery-point retention so protected workloads follow a consistent recovery policy. For this design, the team must define recurring backup frequency and recovery-point retention for the protected workload. That matches the requested operational result.
Incorrect Answers
Answer B is incorrect because Azure Backup can run an additional backup on demand so administrators have a recent recovery point before an upgrade or configuration change. Here the administrator must define recurring backup frequency and recovery-point retention for the protected workload. This is adjacent, but not sufficient.
Answer C is incorrect because Recovery Services vaults manage recovery points and backup operations for supported workloads such as Azure virtual machines. For Azure VM backup, the vault used to protect the workload must be in the same region as the protected data source. The requested outcome is to define recurring backup frequency and recovery-point retention for the protected workload. That behavior differs from the requirement.
Answer D is incorrect because Azure Backup reports use diagnostic data from Recovery Services vaults or Backup vaults sent to a Log Analytics workspace. After data starts flowing, the reporting experience can analyze backup jobs, items, usage, and protection trends across the configured scope. The key requirement is to define recurring backup frequency and recovery-point retention for the protected workload. This would not produce the requested result.
Question 6
A cloud engineer at Woodgrove Bank is working with a design that is standardizing how often protected workloads are backed up and how long each class of recovery point is retained. What is required? Choose ONE.
- Run an on-demand backup before the planned change
- Create or update an Azure Backup policy with the required schedule and retention
- Create a Recovery Services vault in the Azure VM region and configure Azure VM backup
- Configure vault diagnostic settings to send Azure Backup data to Log Analytics for Backup reports
Correct Answer: B
Correct Answer
Answer B is correct because For scheduled protection, the backup policy sets when backups run and how long each class of recovery point remains available. Here the administrator must define recurring backup frequency and recovery-point retention for the protected workload. This meets the deciding technical requirement.
Incorrect Answers
Answer A is incorrect because An on-demand backup creates an extra recovery point outside the regular schedule, which is useful immediately before a risky maintenance change. The deciding need is to define recurring backup frequency and recovery-point retention for the protected workload. That does not meet the deciding constraint.
Answer C is incorrect because Recovery Services vaults manage recovery points and backup operations for supported workloads such as Azure virtual machines. For Azure VM backup, the vault used to protect the workload must be in the same region as the protected data source. Operationally, the team must define recurring backup frequency and recovery-point retention for the protected workload. This solves a different Azure problem.
Answer D is incorrect because Azure Backup reports use diagnostic data from Recovery Services vaults or Backup vaults sent to a Log Analytics workspace. After data starts flowing, the reporting experience can analyze backup jobs, items, usage, and protection trends across the configured scope. The requirement is to define recurring backup frequency and recovery-point retention for the protected workload. That leaves the required outcome unmet.
Question 7
During an operational review at Fourth Coffee, the team finds that the environment is about to modify a workload and wants an extra recoverable point before the maintenance window. What should the administrator use? Choose ONE.
- Create or update an Azure Backup policy with the required schedule and retention
- Use Azure VM File Recovery from the selected recovery point
- Run an on-demand backup before the planned change
- Configure vault diagnostic settings to send Azure Backup data to Log Analytics for Backup reports
Correct Answer: C
Correct Answer
Answer C is correct because Azure Backup can run an additional backup on demand so administrators have a recent recovery point before an upgrade or configuration change. The scenario requires the team to create an additional recent recovery point immediately before a risky maintenance change. That satisfies the scenario without extra changes.
Incorrect Answers
Answer A is incorrect because For scheduled protection, the backup policy sets when backups run and how long each class of recovery point remains available. Operationally, the team must create an additional recent recovery point immediately before a risky maintenance change. This would not produce the requested result.
Answer B is incorrect because Azure VM File Recovery lets an administrator recover individual files or folders from a VM recovery point without first restoring an entire virtual machine, minimizing disruption when only a small set of files is needed. For this design, the team must create an additional recent recovery point immediately before a risky maintenance change. That feature addresses another administration need.
Answer D is incorrect because Azure Backup reports use diagnostic data from Recovery Services vaults or Backup vaults sent to a Log Analytics workspace. After data starts flowing, the reporting experience can analyze backup jobs, items, usage, and protection trends across the configured scope. The scenario requires the team to create an additional recent recovery point immediately before a risky maintenance change. This misses the scenario’s key constraint.
Question 8
A cloud engineer at Tailspin Toys is working with a design that will patch a critical VM in one hour and wants a fresh recovery point before starting even though the scheduled backup already ran earlier. What is required? Choose ONE.
- Create or update an Azure Backup policy with the required schedule and retention
- Use Azure VM File Recovery from the selected recovery point
- Configure vault diagnostic settings to send Azure Backup data to Log Analytics for Backup reports
- Run an on-demand backup before the planned change
Correct Answer: D
Correct Answer
Answer D is correct because An on-demand backup creates an extra recovery point outside the regular schedule, which is useful immediately before a risky maintenance change. The requested outcome is to create an additional recent recovery point immediately before a risky maintenance change. This produces the required Azure behavior.
Incorrect Answers
Answer A is incorrect because For scheduled protection, the backup policy sets when backups run and how long each class of recovery point remains available. For this design, the team must create an additional recent recovery point immediately before a risky maintenance change. That leaves the required outcome unmet.
Answer B is incorrect because Azure VM File Recovery lets an administrator recover individual files or folders from a VM recovery point without first restoring an entire virtual machine, minimizing disruption when only a small set of files is needed. Here the administrator must create an additional recent recovery point immediately before a risky maintenance change. This is adjacent, but not sufficient.
Answer C is incorrect because Azure Backup reports use diagnostic data from Recovery Services vaults or Backup vaults sent to a Log Analytics workspace. After data starts flowing, the reporting experience can analyze backup jobs, items, usage, and protection trends across the configured scope. The requested outcome is to create an additional recent recovery point immediately before a risky maintenance change. That behavior differs from the requirement.
Question 9
During an operational review at A. Datum, the team finds that the environment has one accidentally deleted configuration file and wants to recover it with minimal disruption to the running VM. What should the administrator use? Choose ONE.
- Use Azure VM File Recovery from the selected recovery point
- Restore the Azure VM from the selected recovery point, using the appropriate VM or disk restore option
- Run an on-demand backup before the planned change
- Create or update an Azure Backup policy with the required schedule and retention
Correct Answer: A
Correct Answer
Answer A is correct because Azure VM File Recovery lets an administrator recover individual files or folders from a VM recovery point without first restoring an entire virtual machine, minimizing disruption when only a small set of files is needed. The key requirement is to recover a small set of files from a VM recovery point without restoring the entire virtual machine. That is the best fit here.
Incorrect Answers
Answer B is incorrect because Azure VM restore can create a new VM, restore disks for customized deployment, or in supported scenarios replace existing disks. The selected recovery point provides the protected disk state used by the restore workflow. Here the administrator must recover a small set of files from a VM recovery point without restoring the entire virtual machine. This misses the scenario’s key constraint.
Answer C is incorrect because Azure Backup can run an additional backup on demand so administrators have a recent recovery point before an upgrade or configuration change. The deciding need is to recover a small set of files from a VM recovery point without restoring the entire virtual machine. That does not meet the deciding constraint.
Answer D is incorrect because For scheduled protection, the backup policy sets when backups run and how long each class of recovery point remains available. Operationally, the team must recover a small set of files from a VM recovery point without restoring the entire virtual machine. This solves a different Azure problem.
Question 10
At Trey Research, the team is responding to an accidental file deletion and full virtual-machine restoration would be unnecessarily disruptive. Which option best meets the requirement? Choose ONE.
- Restore the Azure VM from the selected recovery point, using the appropriate VM or disk restore option
- Use Azure VM File Recovery from the selected recovery point
- Run an on-demand backup before the planned change
- Create or update an Azure Backup policy with the required schedule and retention
Correct Answer: B
Correct Answer
Answer B is correct because Azure VM File Recovery lets an administrator recover individual files or folders from a VM recovery point without first restoring an entire virtual machine, minimizing disruption when only a small set of files is needed. The requirement is to recover a small set of files from a VM recovery point without restoring the entire virtual machine. This is the required platform behavior.
Incorrect Answers
Answer A is incorrect because Azure VM restore can create a new VM, restore disks for customized deployment, or in supported scenarios replace existing disks. The selected recovery point provides the protected disk state used by the restore workflow. The scenario requires the team to recover a small set of files from a VM recovery point without restoring the entire virtual machine. That behavior differs from the requirement.
Answer C is incorrect because An on-demand backup creates an extra recovery point outside the regular schedule, which is useful immediately before a risky maintenance change. Operationally, the team must recover a small set of files from a VM recovery point without restoring the entire virtual machine. This would not produce the requested result.
Answer D is incorrect because For scheduled protection, the backup policy sets when backups run and how long each class of recovery point remains available. For this design, the team must recover a small set of files from a VM recovery point without restoring the entire virtual machine. That feature addresses another administration need.
Question 11
An Azure administrator for Tailspin Toys learns that the environment has widespread disk corruption and recovering individual files would not restore the server to a consistent usable state. What should be done? Choose ONE.
- Use Azure VM File Recovery from the selected recovery point
- Run an on-demand backup before the planned change
- Restore the Azure VM from the selected recovery point, using the appropriate VM or disk restore option
- Create or update an Azure Backup policy with the required schedule and retention
Correct Answer: C
Correct Answer
Answer C is correct because Azure VM restore can create a new VM, restore disks for customized deployment, or in supported scenarios replace existing disks. The selected recovery point provides the protected disk state used by the restore workflow. The scenario requires the team to recover the virtual machine or its disks from a selected Azure VM recovery point after broader disk-state loss. That directly meets the stated constraint.
Incorrect Answers
Answer A is incorrect because Azure VM File Recovery lets an administrator recover individual files or folders from a VM recovery point without first restoring an entire virtual machine, minimizing disruption when only a small set of files is needed. The requested outcome is to recover the virtual machine or its disks from a selected Azure VM recovery point after broader disk-state loss. This solves a different Azure problem.
Answer B is incorrect because An on-demand backup creates an extra recovery point outside the regular schedule, which is useful immediately before a risky maintenance change. For this design, the team must recover the virtual machine or its disks from a selected Azure VM recovery point after broader disk-state loss. That leaves the required outcome unmet.
Answer D is incorrect because Azure Backup policies control scheduled backup frequency and recovery-point retention so protected workloads follow a consistent recovery policy. Here the administrator must recover the virtual machine or its disks from a selected Azure VM recovery point after broader disk-state loss. This is adjacent, but not sufficient.
Question 12
At Humongous Insurance, the team lost the VM operating-system disk and needs to reconstruct the protected machine from a known recovery point. Which option best meets the requirement? Choose ONE.
- Use Azure VM File Recovery from the selected recovery point
- Run an on-demand backup before the planned change
- Create or update an Azure Backup policy with the required schedule and retention
- Restore the Azure VM from the selected recovery point, using the appropriate VM or disk restore option
Correct Answer: D
Correct Answer
Answer D is correct because Azure VM restore can create a new VM, restore disks for customized deployment, or in supported scenarios replace existing disks. The selected recovery point provides the protected disk state used by the restore workflow. The requested outcome is to recover the virtual machine or its disks from a selected Azure VM recovery point after broader disk-state loss. This directly implements the requested outcome.
Incorrect Answers
Answer A is incorrect because Azure VM File Recovery lets an administrator recover individual files or folders from a VM recovery point without first restoring an entire virtual machine, minimizing disruption when only a small set of files is needed. The key requirement is to recover the virtual machine or its disks from a selected Azure VM recovery point after broader disk-state loss. That feature addresses another administration need.
Answer B is incorrect because Azure Backup can run an additional backup on demand so administrators have a recent recovery point before an upgrade or configuration change. Here the administrator must recover the virtual machine or its disks from a selected Azure VM recovery point after broader disk-state loss. This misses the scenario’s key constraint.
Answer C is incorrect because Azure Backup policies control scheduled backup frequency and recovery-point retention so protected workloads follow a consistent recovery policy. The deciding need is to recover the virtual machine or its disks from a selected Azure VM recovery point after broader disk-state loss. That does not meet the deciding constraint.
Question 13
An Azure administrator for Adventure Works learns that the environment must survive a primary-region outage with orchestrated recovery of protected Azure VMs in another Azure region. What should be done? Choose ONE.
- Enable Azure Site Recovery replication to the secondary region and configure the target resources
- Create a Recovery Services vault in the Azure VM region and configure Azure VM backup
- Create or update an Azure Backup policy with the required schedule and retention
- Run an on-demand backup before the planned change
Correct Answer: A
Correct Answer
Answer A is correct because Azure Site Recovery continuously replicates protected workloads to the configured recovery location and orchestrates recovery. Azure-to-Azure disaster recovery requires replication and target-region settings before a regional outage occurs. The key requirement is to prepare an Azure workload for regional disaster recovery by continuously replicating it to the configured secondary region. That matches the requested operational result.
Incorrect Answers
Answer B is incorrect because Recovery Services vaults manage recovery points and backup operations for supported workloads such as Azure virtual machines. For Azure VM backup, the vault used to protect the workload must be in the same region as the protected data source. The requirement is to prepare an Azure workload for regional disaster recovery by continuously replicating it to the configured secondary region. This is adjacent, but not sufficient.
Answer C is incorrect because Azure Backup policies control scheduled backup frequency and recovery-point retention so protected workloads follow a consistent recovery policy. The scenario requires the team to prepare an Azure workload for regional disaster recovery by continuously replicating it to the configured secondary region. That behavior differs from the requirement.
Answer D is incorrect because Azure Backup can run an additional backup on demand so administrators have a recent recovery point before an upgrade or configuration change. Operationally, the team must prepare an Azure workload for regional disaster recovery by continuously replicating it to the configured secondary region. This would not produce the requested result.
Question 14
A cloud engineer at A. Datum is working with a design that is implementing a recovery site with target networking and replication configured before production is affected. What is required? Choose ONE.
- Create a Recovery Services vault in the Azure VM region and configure Azure VM backup
- Enable Azure Site Recovery replication to the secondary region and configure the target resources
- Create or update an Azure Backup policy with the required schedule and retention
- Run an on-demand backup before the planned change
Correct Answer: B
Correct Answer
Answer B is correct because Azure Site Recovery continuously replicates protected workloads to the configured recovery location and orchestrates recovery. Azure-to-Azure disaster recovery requires replication and target-region settings before a regional outage occurs. For this design, the team must prepare an Azure workload for regional disaster recovery by continuously replicating it to the configured secondary region. This meets the deciding technical requirement.
Incorrect Answers
Answer A is incorrect because Recovery Services vaults manage recovery points and backup operations for supported workloads such as Azure virtual machines. For Azure VM backup, the vault used to protect the workload must be in the same region as the protected data source. The scenario requires the team to prepare an Azure workload for regional disaster recovery by continuously replicating it to the configured secondary region. That does not meet the deciding constraint.
Answer C is incorrect because Azure Backup policies control scheduled backup frequency and recovery-point retention so protected workloads follow a consistent recovery policy. The requested outcome is to prepare an Azure workload for regional disaster recovery by continuously replicating it to the configured secondary region. This solves a different Azure problem.
Answer D is incorrect because An on-demand backup creates an extra recovery point outside the regular schedule, which is useful immediately before a risky maintenance change. For this design, the team must prepare an Azure workload for regional disaster recovery by continuously replicating it to the configured secondary region. That leaves the required outcome unmet.
Question 15
During an operational review at Humongous Insurance, the team finds that the environment is conducting a quarterly DR exercise and wants temporary recovered VMs that can be cleaned up after validation. What should the administrator use? Choose ONE.
- Run Site Recovery failover to an appropriate recovery point, validate the recovered workload, and then commit
- Enable Azure Site Recovery replication to the secondary region and configure the target resources
- Run an Azure Site Recovery test failover into an isolated test virtual network
- Restore the Azure VM from the selected recovery point, using the appropriate VM or disk restore option
Correct Answer: C
Correct Answer
Answer C is correct because A Site Recovery test failover validates disaster-recovery readiness without performing the production failover. Microsoft recommends an isolated test network so the recovery drill does not create identity, address, or service conflicts with production. Here the administrator must validate the Site Recovery plan in a drill without performing the production regional failover. That satisfies the scenario without extra changes.
Incorrect Answers
Answer A is incorrect because A Site Recovery failover starts the workload in the recovery location from the selected recovery point. After the recovered application is validated, Commit finalizes that recovery point; reprotection is then used for the next replication direction as required. The requested outcome is to validate the Site Recovery plan in a drill without performing the production regional failover. This would not produce the requested result.
Answer B is incorrect because Azure Site Recovery continuously replicates protected workloads to the configured recovery location and orchestrates recovery. Azure-to-Azure disaster recovery requires replication and target-region settings before a regional outage occurs. The key requirement is to validate the Site Recovery plan in a drill without performing the production regional failover. That feature addresses another administration need.
Answer D is incorrect because Azure VM restore can create a new VM, restore disks for customized deployment, or in supported scenarios replace existing disks. The selected recovery point provides the protected disk state used by the restore workflow. Here the administrator must validate the Site Recovery plan in a drill without performing the production regional failover. This misses the scenario’s key constraint.
Question 16
A cloud engineer at Wingtip Toys is working with a design that needs evidence that replicated VMs can start and applications can be tested while production continues to run. What is required? Choose ONE.
- Run Site Recovery failover to an appropriate recovery point, validate the recovered workload, and then commit
- Enable Azure Site Recovery replication to the secondary region and configure the target resources
- Restore the Azure VM from the selected recovery point, using the appropriate VM or disk restore option
- Run an Azure Site Recovery test failover into an isolated test virtual network
Correct Answer: D
Correct Answer
Answer D is correct because A Site Recovery test failover validates disaster-recovery readiness without performing the production failover. Microsoft recommends an isolated test network so the recovery drill does not create identity, address, or service conflicts with production. The deciding need is to validate the Site Recovery plan in a drill without performing the production regional failover. This produces the required Azure behavior.
Incorrect Answers
Answer A is incorrect because A Site Recovery failover starts the workload in the recovery location from the selected recovery point. After the recovered application is validated, Commit finalizes that recovery point; reprotection is then used for the next replication direction as required. The key requirement is to validate the Site Recovery plan in a drill without performing the production regional failover. That leaves the required outcome unmet.
Answer B is incorrect because Azure Site Recovery continuously replicates protected workloads to the configured recovery location and orchestrates recovery. Azure-to-Azure disaster recovery requires replication and target-region settings before a regional outage occurs. The requirement is to validate the Site Recovery plan in a drill without performing the production regional failover. This is adjacent, but not sufficient.
Answer C is incorrect because Azure VM restore can create a new VM, restore disks for customized deployment, or in supported scenarios replace existing disks. The selected recovery point provides the protected disk state used by the restore workflow. The scenario requires the team to validate the Site Recovery plan in a drill without performing the production regional failover. That behavior differs from the requirement.
Question 17
During an operational review at City Power & Light, the team finds that the environment has lost the primary region and must start the replicated application in the recovery region from the chosen Site Recovery point. What should the administrator use? Choose ONE.
- Run Site Recovery failover to an appropriate recovery point, validate the recovered workload, and then commit
- Run an Azure Site Recovery test failover into an isolated test virtual network
- Restore the Azure VM from the selected recovery point, using the appropriate VM or disk restore option
- Run an on-demand backup before the planned change
Correct Answer: A
Correct Answer
Answer A is correct because A Site Recovery failover starts the workload in the recovery location from the selected recovery point. After the recovered application is validated, Commit finalizes that recovery point; reprotection is then used for the next replication direction as required. Operationally, the team must recover the protected workload in the secondary location during an actual outage and finalize the validated recovery point. That is the best fit here.
Incorrect Answers
Answer B is incorrect because A Site Recovery test failover validates disaster-recovery readiness without performing the production failover. Microsoft recommends an isolated test network so the recovery drill does not create identity, address, or service conflicts with production. For this design, the team must recover the protected workload in the secondary location during an actual outage and finalize the validated recovery point. This misses the scenario’s key constraint.
Answer C is incorrect because Azure VM restore can create a new VM, restore disks for customized deployment, or in supported scenarios replace existing disks. The selected recovery point provides the protected disk state used by the restore workflow. The scenario requires the team to recover the protected workload in the secondary location during an actual outage and finalize the validated recovery point. That does not meet the deciding constraint.
Answer D is incorrect because Azure Backup can run an additional backup on demand so administrators have a recent recovery point before an upgrade or configuration change. The requested outcome is to recover the protected workload in the secondary location during an actual outage and finalize the validated recovery point. This solves a different Azure problem.
Question 18
At Adventure Works, the team must select a Site Recovery recovery point, bring up the workload, validate it, and finalize the recovery after service is restored. Which option best meets the requirement? Choose ONE.
- Run an Azure Site Recovery test failover into an isolated test virtual network
- Run Site Recovery failover to an appropriate recovery point, validate the recovered workload, and then commit
- Restore the Azure VM from the selected recovery point, using the appropriate VM or disk restore option
- Run an on-demand backup before the planned change
Correct Answer: B
Correct Answer
Answer B is correct because A Site Recovery failover starts the workload in the recovery location from the selected recovery point. After the recovered application is validated, Commit finalizes that recovery point; reprotection is then used for the next replication direction as required. For this design, the team must recover the protected workload in the secondary location during an actual outage and finalize the validated recovery point. This is the required platform behavior.
Incorrect Answers
Answer A is incorrect because A Site Recovery test failover validates disaster-recovery readiness without performing the production failover. Microsoft recommends an isolated test network so the recovery drill does not create identity, address, or service conflicts with production. Here the administrator must recover the protected workload in the secondary location during an actual outage and finalize the validated recovery point. That behavior differs from the requirement.
Answer C is incorrect because Azure VM restore can create a new VM, restore disks for customized deployment, or in supported scenarios replace existing disks. The selected recovery point provides the protected disk state used by the restore workflow. The requested outcome is to recover the protected workload in the secondary location during an actual outage and finalize the validated recovery point. This would not produce the requested result.
Answer D is incorrect because An on-demand backup creates an extra recovery point outside the regular schedule, which is useful immediately before a risky maintenance change. The key requirement is to recover the protected workload in the secondary location during an actual outage and finalize the validated recovery point. That feature addresses another administration need.
Question 19
An Azure administrator for Wingtip Toys learns that the environment is building a monitoring baseline that includes analytics over vault diagnostic data plus service-generated Azure Monitor alerts. What should be done? Choose TWO.
- Configure vault diagnostic settings to send Azure Backup data to Log Analytics for Backup reports
- Create or update an Azure Backup policy with the required schedule and retention
- Run an on-demand backup before the planned change
- Use Azure Monitor built-in alerts for Azure Backup or Site Recovery job and protection failures
- Restore the Azure VM from the selected recovery point, using the appropriate VM or disk restore option
Correct Answers: A, D
Correct Answers
Answer A is correct because Azure Backup reports use diagnostic data from Recovery Services vaults or Backup vaults sent to a Log Analytics workspace. After data starts flowing, the reporting experience can analyze backup jobs, items, usage, and protection trends across the configured scope. Here the administrator must provide centralized reporting from vault diagnostic data and operational alerts for backup or Site Recovery failures. That directly meets the stated constraint.
Answer D is correct because Azure Backup and Site Recovery integrate with Azure Monitor built-in alerts for operational and security conditions. These alerts provide centralized monitoring and can be connected to action groups for notification and automation. The deciding need is to provide centralized reporting from vault diagnostic data and operational alerts for backup or Site Recovery failures. This produces the required Azure behavior.
Incorrect Answers
Answer B is incorrect because For scheduled protection, the backup policy sets when backups run and how long each class of recovery point remains available. The key requirement is to provide centralized reporting from vault diagnostic data and operational alerts for backup or Site Recovery failures. That leaves the required outcome unmet.
Answer C is incorrect because Azure Backup can run an additional backup on demand so administrators have a recent recovery point before an upgrade or configuration change. The requirement is to provide centralized reporting from vault diagnostic data and operational alerts for backup or Site Recovery failures. This is adjacent, but not sufficient.
Answer E is incorrect because Azure VM restore can create a new VM, restore disks for customized deployment, or in supported scenarios replace existing disks. The selected recovery point provides the protected disk state used by the restore workflow. The scenario requires the team to provide centralized reporting from vault diagnostic data and operational alerts for backup or Site Recovery failures. That behavior differs from the requirement.
Question 20
At Northwind Traders, the team needs cross-vault Backup reports in Log Analytics and also wants operations alerted when protection jobs fail. Which option best meets the requirement? Choose TWO.
- Create or update an Azure Backup policy with the required schedule and retention
- Configure vault diagnostic settings to send Azure Backup data to Log Analytics for Backup reports
- Run an on-demand backup before the planned change
- Restore the Azure VM from the selected recovery point, using the appropriate VM or disk restore option
- Use Azure Monitor built-in alerts for Azure Backup or Site Recovery job and protection failures
Correct Answers: B, E
Correct Answers
Answer B is correct because Azure Backup reports use diagnostic data from Recovery Services vaults or Backup vaults sent to a Log Analytics workspace. After data starts flowing, the reporting experience can analyze backup jobs, items, usage, and protection trends across the configured scope. The deciding need is to provide centralized reporting from vault diagnostic data and operational alerts for backup or Site Recovery failures. This directly implements the requested outcome.
Answer E is correct because Azure Backup and Site Recovery integrate with Azure Monitor built-in alerts for operational and security conditions. These alerts provide centralized monitoring and can be connected to action groups for notification and automation. Operationally, the team must provide centralized reporting from vault diagnostic data and operational alerts for backup or Site Recovery failures. That is the best fit here.
Incorrect Answers
Answer A is incorrect because Azure Backup policies control scheduled backup frequency and recovery-point retention so protected workloads follow a consistent recovery policy. For this design, the team must provide centralized reporting from vault diagnostic data and operational alerts for backup or Site Recovery failures. This misses the scenario’s key constraint.
Answer C is incorrect because Azure Backup can run an additional backup on demand so administrators have a recent recovery point before an upgrade or configuration change. The scenario requires the team to provide centralized reporting from vault diagnostic data and operational alerts for backup or Site Recovery failures. That does not meet the deciding constraint.
Answer D is incorrect because Azure VM restore can create a new VM, restore disks for customized deployment, or in supported scenarios replace existing disks. The selected recovery point provides the protected disk state used by the restore workflow. The requested outcome is to provide centralized reporting from vault diagnostic data and operational alerts for backup or Site Recovery failures. This solves a different Azure problem.