PMI PMP Project Management Professional Exam Dumps and Practice Test Questions Set 6 Q101-120

Visit here for our full PMI PMP exam dumps and practice test questions.

Question 101

In scope management, what is the purpose of scope verification?

A) To document scope changes 

B) To obtain formal acceptance of completed deliverables from stakeholders 

C) To create the WBS 

D) To identify project risks

Answer: B) To obtain formal acceptance of completed deliverables from stakeholders

Explanation: 

Scope verification obtains formal acceptance of completed project deliverables from customers or sponsors through systematic review and acceptance processes. This validation confirms that deliverables meet requirements and acceptance criteria established during planning and documented in scope baselines. Formal acceptance provides clear confirmation that project obligations have been fulfilled and prevents disputes about whether commitments were adequately satisfied.

The verification process involves presenting completed deliverables to appropriate stakeholders along with evidence demonstrating that acceptance criteria have been met. This might include inspection results, test reports, performance data, compliance certifications, or other documentation proving that deliverables satisfy agreed standards. Stakeholders review deliverables and documentation verifying that requirements are satisfied before granting formal acceptance.

Acceptance documentation creates official record that deliverables were reviewed and accepted providing protection for the project team and closure for that portion of project scope. Signed acceptance forms, formal approval notifications, or documented acceptance decisions provide evidence that stakeholder obligations to review and accept were fulfilled and that deliverables passed scrutiny. This documentation is essential for project closure and protects against later claims that deliverables were inadequate.

Question 102

What is a project baseline?

A) The original project charter 

B) The approved version of a project plan used for comparison with actual results 

C) The final project report 

D) A list of project assumptions

Answer: B) The approved version of a project plan used for comparison with actual results

Explanation: 

A project baseline is the approved version of a project plan that serves as the reference point for measuring and comparing actual project performance. Baselines are established for scope, schedule, and cost creating stable references against which variances are measured enabling objective performance assessment. Baselines can only be changed through formal change control processes preventing baseline drift that would undermine their utility as performance measurement references.

The performance measurement baseline integrates scope, schedule, and cost baselines into a time-phased budget representing authorized work, timing, and funding. This integrated baseline enables earned value management and other performance measurement techniques that compare planned versus actual performance revealing variances requiring management attention. Without baselines, performance assessment lacks objective references and becomes subjective or arbitrary.

Baseline establishment requires formal approval from appropriate authorities typically including project sponsors and key stakeholders. This approval signifies organizational commitment to the plan and agreement that the baseline represents realistic and achievable project direction. Formal approval also establishes the baseline’s authority as the reference for performance measurement and change control. Unapproved plans lack the standing to serve as official baselines regardless of their quality.

Question 103

In stakeholder management, what is a stakeholder engagement assessment matrix?

A) A financial analysis tool 

B) A tool to compare current and desired stakeholder engagement levels 

C) A method for creating Gantt charts 

D) A risk assessment technique

Answer: B) A tool to compare current and desired stakeholder engagement levels

Explanation: 

The stakeholder engagement assessment matrix compares current stakeholder engagement levels with desired engagement levels for each stakeholder or stakeholder group enabling targeted engagement strategies. This analysis reveals where stakeholders are more engaged or less engaged than desired for project success guiding efforts to increase engagement of under-engaged stakeholders or manage expectations of over-engaged stakeholders. The matrix makes engagement planning systematic and strategic rather than reactive.

Question 104

What is the primary purpose of a lessons learned register?

A) To document team member performance reviews 

B) To capture knowledge gained during the project for future reference and improvement 

C) To track project expenses 

D) To schedule project meetings

Answer: B) To capture knowledge gained during the project for future reference and improvement

Explanation:

The lessons learned register captures knowledge gained throughout the project including challenges encountered, successes achieved, problems solved, and insights discovered that have value for current project improvement and future organizational learning. This knowledge management tool transforms project experience into organizational assets preventing repeated mistakes and enabling replication of successful approaches. Effective lessons learned documentation significantly improves organizational project management maturity over time.

Knowledge capture should occur throughout the project lifecycle rather than only at project closure. Early lessons remain fresh and actionable while end-of-project documentation often suffers from faded memories and unavailable team members. Continuous lessons documentation during project execution captures insights when they’re most accurate and enables applying lessons to current project work improving performance in real-time rather than only benefiting future projects.

Lesson categorization by knowledge area, project phase, or problem type enhances retrieval and application. Well-organized lessons learned repositories enable future project teams to efficiently find relevant insights rather than searching through unstructured narratives. Categories might include estimation approaches, risk management techniques, stakeholder engagement strategies, technical solutions, or vendor management practices. This organization transforms raw experience documentation into practical reference material.

Question 105

What does the critical path represent in a project schedule?

A) The shortest possible project duration 

B) The longest path of activities determining minimum project duration 

C) The most expensive sequence of activities 

D) The least important activities in the project

Answer: B) The longest path of activities determining minimum project duration

Explanation: 

The critical path represents the longest sequence of dependent activities from project start to finish determining the minimum possible project duration. Activities on the critical path have zero schedule flexibility meaning any delay in critical path activities directly extends overall project completion date. Understanding the critical path enables focused schedule management and risk mitigation on activities that directly impact project timing.

Critical path calculation uses network diagram logic and activity duration estimates to identify which activity sequences constrain project duration. Multiple paths might exist through the project network but the longest path determines when the project can finish because all paths must complete before the project is done. Even if some work finishes early, the project cannot complete until the longest path is finished.

Schedule compression efforts must focus on critical path activities to reduce project duration. Accelerating non-critical activities doesn’t shorten overall project timeline regardless of how much those specific activities are accelerated because other longer paths still constrain completion. Crashing or fast-tracking critical path activities can reduce project duration though often at increased cost or risk. This critical path focus prevents wasting schedule compression resources on activities that don’t affect project completion.

Question 106

In quality management, what is the cost of conformance?

A) The cost of meeting quality requirements through prevention and appraisal 

B) The cost of poor quality and rework 

C) Only the cost of final inspection 

D) The profit from selling quality products

Answer: A) The cost of meeting quality requirements through prevention and appraisal

Explanation: 

Cost of conformance represents money spent during the project to avoid failures including prevention costs and appraisal costs. Prevention costs include quality planning, process documentation, training, and quality assurance activities that prevent defects from occurring. Appraisal costs include inspection, testing, audits, and quality reviews that detect defects before delivery to customers. These proactive quality investments aim to ensure deliverables meet requirements and avoid costly failures.

Prevention costs deliver the highest return on quality investment by stopping defects before they occur. Money spent on clear requirements, effective design reviews, capable processes, trained personnel, and appropriate tools prevents defects that would otherwise require expensive detection and correction. Prevention represents building quality into work from the beginning rather than inspecting quality in afterward. Organizations with mature quality cultures invest heavily in prevention achieving lower total quality costs.

Appraisal costs detect defects that prevention activities failed to stop enabling correction before deliverables reach customers. While less cost-effective than prevention, appraisal provides essential verification that quality standards are met and catches defects that inevitably slip through even good prevention. Testing, inspection, and review activities generate appraisal costs but prove far less expensive than external failure costs when defects reach customers. Optimal quality strategies balance prevention, appraisal, and failure costs minimizing total cost of quality.

Question 107

What is the purpose of resource leveling in project scheduling?

A) To increase project costs 

B) To balance resource demand with resource availability by adjusting activity timing 

C) To eliminate all project risks 

D) To reduce project scope

Answer: B) To balance resource demand with resource availability by adjusting activity timing

Explanation: 

Resource leveling balances resource demand with resource availability by adjusting activity start and finish dates to prevent resource over-allocation while managing schedule impact. This optimization technique resolves situations where the schedule requires more resources during certain periods than are available by shifting non-critical activities to periods with resource availability. Resource leveling produces realistic schedules that can actually be executed with available resources rather than theoretical schedules assuming unlimited resources.

Resource over-allocation occurs when the schedule requires more of a resource during some time period than is available. A person might be assigned to multiple activities scheduled simultaneously, or equipment might be needed by concurrent activities. These over-allocations represent scheduling conflicts that cannot be executed as planned. Resource leveling identifies over-allocations and resolves them through rescheduling activities that have sufficient float to be moved without affecting project completion date.

The leveling process typically extends project duration because resolving resource conflicts by delaying activities often pushes some activities onto the critical path. Activities with float can be delayed to resolve resource conflicts but this float consumption sometimes creates new critical paths. The tradeoff between resource availability and schedule represents a fundamental project constraint that leveling makes explicit. Organizations must decide whether to accept longer schedules with available resources or secure additional resources to maintain compressed schedules.

Question 108

What is a project charter’s relationship to the business case?

A) They are identical documents 

B) The charter summarizes and references the business case providing project authorization 

C) The charter replaces the need for a business case 

D) The charter is created before the business case

Answer: B) The charter summarizes and references the business case providing project authorization

Explanation: 

The project charter summarizes key information from the business case and formally authorizes the project based on the business case justification. The business case provides comprehensive analysis of project rationale, expected benefits, costs, alternatives, and recommendations supporting the investment decision. The charter references this justification while adding project-specific information like assigned project manager, high-level requirements, and general timeline creating the bridge between strategic business decisions and project execution.

Business case development typically precedes charter creation as part of the project selection process. Organizations evaluate potential projects through business case analysis determining which initiatives provide sufficient value to justify investment. Approved business cases lead to project authorization through charter issuance. The charter confirms that business case analysis supports moving forward and formally designates the project manager who will plan and execute the project delivering the benefits promised in the business case.

The charter provides condensed reference to business case justification making the project’s strategic rationale accessible without requiring stakeholders to review lengthy business case documentation. Charter readers understand why the project exists, what benefits it should deliver, and how it aligns with organizational strategy through charter summary of business case essentials. This accessibility ensures that project participants understand the business context driving their work rather than just focusing on technical execution.

Question 109

In earned value management, what is the formula for Cost Variance (CV)?

A) CV = EV – PV 

B) CV = EV – AC 

C) CV = AC – EV 

D) CV = PV – AC

Answer: B) CV = EV – AC

Explanation: Cost Variance is calculated as Earned Value minus Actual Cost revealing whether the project is under or over budget for work completed. Positive CV indicates favorable cost performance where work is accomplished for less than budgeted cost. Negative CV indicates unfavorable cost performance where work costs more than budgeted. Cost variance provides objective measure of cost efficiency independent of schedule performance.

Earned Value represents the budgeted cost of work actually completed measuring how much work has been accomplished in dollar value terms. Actual Cost represents what was actually spent to complete that work. The difference between these values reveals cost efficiency. If work budgeted at $100,000 is completed for $90,000 actual cost, the $10,000 positive cost variance indicates efficient cost performance. If the same work costs $110,000, the negative $10,000 cost variance signals cost overruns.

Cost variance complements Schedule Variance providing comprehensive earned value performance assessment. Projects might have favorable cost variance but unfavorable schedule variance indicating efficient work execution but slower pace than planned. Conversely, favorable schedule variance with unfavorable cost variance suggests accelerated work at premium cost. Understanding both variances together provides complete picture of project performance across the schedule-cost trade-off spectrum.

Question 110

What is the purpose of a project scope statement?

A) To list all project stakeholders 

B) To provide detailed description of project scope, deliverables, and acceptance criteria 

C) To document project team assignments 

D) To calculate earned value metrics

Answer: B) To provide detailed description of project scope, deliverables, and acceptance criteria

Explanation: 

The project scope statement provides detailed description of project and product scope including deliverables, acceptance criteria, project boundaries, constraints, and assumptions. This comprehensive scope definition establishes shared understanding among all stakeholders about what the project will and will not deliver preventing misunderstandings that cause conflicts and rework. The scope statement serves as the primary reference for scope validation and scope control throughout project execution.

Deliverable descriptions specify what tangible or intangible products, services, or results the project will produce. These descriptions provide sufficient detail to enable work planning, cost estimation, and ultimately deliverable validation. Clear deliverable descriptions answer questions about functionality, features, characteristics, and quality attributes preventing ambiguity about what the project commits to produce. Incomplete deliverable descriptions lead to mismatched expectations and stakeholder dissatisfaction.

Acceptance criteria define the conditions that deliverables must satisfy for stakeholders to accept them as complete. These criteria provide objective standards for determining whether requirements are met removing subjectivity from acceptance decisions. Well-defined acceptance criteria prevent disputes about deliverable adequacy by establishing clear measurable standards that all parties agreed to during planning. Criteria might address functionality, performance, quality, compatibility, or other characteristics critical to stakeholder satisfaction.

Question 111

What is the difference between validated deliverables and accepted deliverables?

A) There is no difference 

B) Validated deliverables have passed quality control; accepted deliverables have been formally approved by stakeholders 

C) Accepted deliverables are tested; validated deliverables are not 

D) Validated deliverables cost more than accepted deliverables

Answer: B) Validated deliverables have passed quality control; accepted deliverables have been formally approved by stakeholders

Explanation: 

Validated deliverables have completed quality control inspection and testing confirming they meet specifications and quality standards but have not yet received formal customer or sponsor acceptance. Accepted deliverables have undergone validation and subsequently received formal stakeholder approval through scope verification processes. This distinction separates internal quality verification from external stakeholder acceptance representing two essential but different aspects of deliverable completion.

Validation through Control Quality ensures deliverables meet technical requirements and quality standards before presenting to stakeholders for acceptance. The project team performs testing, inspection, and review verifying that work products satisfy specifications and perform as required. This internal validation catches defects enabling correction before stakeholders see deliverables. Presenting validated deliverables for acceptance demonstrates professional work and protects the project team from acceptance rejection due to quality failures.

Acceptance through Validate Scope involves stakeholders reviewing validated deliverables and formally confirming they satisfy agreed requirements and acceptance criteria. Even validated deliverables meeting all technical specifications might be rejected if they don’t meet stakeholder needs or if acceptance criteria were inadequate. Stakeholder acceptance represents the ultimate determination of deliverable adequacy from the customer perspective. Formal acceptance provides project closure for completed scope elements and often triggers payment or resource release.

Question 112

In project risk management, what is risk tolerance?

A) The degree of risk an organization is willing to accept 

B) The lowest possible risk level 

C) The cost of risk mitigation 

D) The number of risks in the risk register

Answer: A) The degree of risk an organization is willing to accept

Explanation: 

Risk tolerance defines the degree, amount, or volume of risk that an organization or individual is willing to withstand. This threshold guides risk response decisions determining which risks require active response and which risks can be accepted. Risk tolerance varies by organization, stakeholder, and risk type reflecting different comfort levels with uncertainty and potential negative outcomes. Understanding risk tolerance ensures risk management efforts align with organizational and stakeholder preferences.

Organizations with low risk tolerance accept minimal uncertainty requiring aggressive risk mitigation even for relatively minor risks. These organizations might operate in highly regulated environments, deal with safety-critical applications, or have limited capacity to absorb losses. Risk responses in low-tolerance environments emphasize risk avoidance and extensive mitigation accepting higher costs to minimize uncertainty. Conservative risk cultures prioritize safety and predictability over potential gains from accepting risk.

High risk tolerance organizations accept greater uncertainty in exchange for potential rewards. These organizations might operate in dynamic competitive environments where innovation requires accepting risk, have strong financial positions enabling them to absorb potential losses, or pursue aggressive growth strategies. Risk responses in high-tolerance environments might accept more risks or implement lighter mitigation focusing resources on only the most severe threats. Risk tolerance should be explicitly documented preventing conflicts when individual preferences differ from organizational standards.

Question 113

What is the purpose of decomposition in creating a Work Breakdown Structure?

A) To increase project costs 

B) To break down project deliverables into smaller, more manageable work components 

C) To eliminate project risks 

D) To extend project duration

Answer: B) To break down project deliverables into smaller, more manageable work components

Explanation: 

Decomposition systematically subdivides project deliverables and project work into smaller, more manageable components until work packages at appropriate detail levels are defined. This progressive breakdown continues until components are small enough to be realistically estimated, assigned, tracked, and completed within reasonable timeframes. Decomposition transforms overwhelming project scope into comprehensible pieces enabling effective planning and management.

The decomposition process begins with major deliverables identified in project scope and progressively breaks them into sub-deliverables, components, and ultimately work packages. Each level represents complete decomposition of the level above with all child elements combining to equal the parent element. This hierarchical structure provides multiple levels of aggregation enabling detailed planning at work package levels while supporting summary reporting at higher levels. The structure accommodates different stakeholder needs for detail versus overview.

Stopping criteria determine when decomposition is sufficient and further breakdown unnecessary. Work packages should be small enough to estimate reliably, assign to individuals or small teams, complete within one or two reporting periods, and track progress effectively. However, excessive decomposition into overly small pieces creates management overhead without providing meaningful planning benefit. The appropriate level of detail balances precision against manageability varying by project complexity, duration, and organizational norms.

Question 114

What is the purpose of a milestone chart?

A) To track detailed task-level activities 

B) To show significant points or achievements in the project schedule 

C) To analyze project costs 

D) To document quality metrics

Answer: B) To show significant points or achievements in the project schedule

Explanation: 

A milestone chart displays significant points or achievements in the project timeline typically showing key deliverable completions, phase transitions, decision points, or major reviews without the activity detail of full schedules. This high-level view emphasizes important project events enabling stakeholders to quickly understand major accomplishments and upcoming critical dates without being overwhelmed by detailed activity information. Milestone charts provide executive-friendly schedule communication focused on what matters most to senior stakeholders.

Milestones represent zero-duration events marking important points in project progression rather than work activities with duration. Typical milestones include requirements approval, design completion, prototype delivery, testing completion, and final acceptance. These achievement markers provide clear measurable indicators of project progress enabling straightforward status communication. Achieving milestones generates team motivation and demonstrates tangible progress even when overall project completion remains distant.

Milestone emphasis helps focus team and stakeholder attention on critical project events rather than being lost in detailed activity tracking. By highlighting what really matters, milestone charts direct energy toward achieving the next significant accomplishment. This focus prevents teams from losing sight of important objectives amid daily tactical work. Milestone tracking also provides early warning when key achievements are threatened enabling proactive intervention before schedule problems become severe.

Question 115

In agile methodologies, what is the definition of “done”?

A) When funding runs out 

B) The agreed criteria that must be met for work to be considered complete 

C) When the project manager says so 

D) After one year of development

Answer: B) The agreed criteria that must be met for work to be considered complete

Explanation: The definition of done is the agreed set of criteria that work must satisfy to be considered complete including quality standards, testing requirements, documentation, and any other conditions necessary for potentially shippable increments. This shared understanding prevents confusion about work completeness ensuring consistency across team members and preventing false completion claims for work that doesn’t meet quality standards. A clear definition of done maintains quality discipline in fast-paced agile environments.

Done criteria typically include requirements met, code written and reviewed, unit tests passed, integration testing completed, documentation updated, acceptance criteria verified, and defects resolved. These comprehensive standards ensure that calling work done means it’s actually ready for potential release not just that coding is finished. Without rigorous done definitions, technical debt accumulates as partially complete work is declared done leaving testing, documentation, and quality work for later.

Team agreement on done definitions prevents individual interpretation variances where different team members apply different completeness standards. Collaborative definition development ensures shared understanding and commitment to quality standards. Regular retrospective reviews might refine done definitions as teams mature or as projects reveal gaps in existing criteria. The definition evolves maintaining relevance while providing stability within iterations. Documented done definitions provide objective references preventing arguments about whether work is complete.

Question 116

What is the purpose of fast tracking in schedule compression?

A) To increase project costs 

B) To perform activities in parallel that would normally be done in sequence 

C) To eliminate project activities 

D) To extend the project timeline

Answer: B) To perform activities in parallel that would normally be done in sequence

Explanation: 

Fast tracking compresses project schedules by performing activities in parallel that would normally be done sequentially reducing overall project duration without necessarily adding resources. This technique modifies activity dependencies allowing successor activities to begin before predecessor activities are fully complete. Fast tracking accelerates schedules but increases risk because work proceeds with incomplete information that normally would be available if sequences were maintained.

Dependency examination identifies where mandatory sequential relationships might be relaxed to enable overlapping work. Some dependencies are truly mandatory based on physical or logical requirements that cannot be violated. Other dependencies represent preferences or risk mitigation strategies that can be challenged when schedule compression is critical. Fast tracking opportunities exist where activities have some natural overlap potential such as beginning detailed design before all requirements are finalized or starting construction before all design drawings are complete.

Risk assessment is critical for fast tracking decisions because parallel work based on incomplete predecessor information creates rework risk. If initial assumptions prove wrong when predecessor work completes, parallel work done based on those assumptions might require revision. The schedule acceleration benefit must justify the rework risk and potential cost increases. Fast tracking works best when rework probability is low or rework costs are acceptable given schedule urgency. High rework probability or costs make fast tracking uneconomical despite schedule benefits.

Question 117

What is the primary purpose of configuration management in projects?

A) To increase project costs 

B) To systematically manage changes to project deliverables and documentation 

C) To eliminate all project meetings 

D) To reduce stakeholder involvement

Answer: B) To systematically manage changes to project deliverables and documentation

Explanation: 

Configuration management systematically identifies, controls, and tracks project deliverables and documentation ensuring that current approved versions are available and used while previous versions are retained for reference or recovery. This discipline prevents confusion about which versions are authoritative, enables reconstruction of any configuration, supports change impact analysis, and maintains traceability from requirements through implementation. Configuration management becomes increasingly critical as project complexity and team size grow.

Version control identifies and labels each version of project artifacts enabling clear differentiation between draft, approved, and superseded versions. Naming conventions, version numbers, and status indicators communicate version authority preventing team members from accidentally working with outdated documents or deliverables. Version control systems automate much of this tracking but the underlying discipline of creating identifiable versions and managing their status applies regardless of automation level.

Change control ensures that modifications to baselined deliverables or documents follow approved processes preventing unauthorized changes that might introduce defects or create inconsistencies. When deliverables reach approved baseline status, further changes require formal evaluation, approval, and controlled implementation. This discipline prevents freelance modifications that seem beneficial locally but create problems elsewhere. Change control becomes especially important when multiple team members work on related artifacts where uncoordinated changes create integration problems.

Question 118

In stakeholder management, what is stakeholder mapping?

A) Creating geographic maps of stakeholder locations 

B) Analyzing and categorizing stakeholders based on power, interest, and other factors 

C) Eliminating difficult stakeholders from projects 

D) Creating organization charts

Answer: B) Analyzing and categorizing stakeholders based on power, interest, and other factors

Explanation: Stakeholder mapping analyzes and categorizes stakeholders based on dimensions like power, interest, influence, impact, or attitude creating visual representations that guide engagement strategies. Common mapping approaches include power/interest grids, influence/impact matrices, or salience models considering legitimacy, urgency, and power. These analytical frameworks help project managers understand stakeholder landscapes and develop appropriate engagement approaches for different stakeholder categories.

Power-interest grids represent one widely used mapping technique plotting stakeholders on two dimensions measuring their power to affect project outcomes and their interest in project activities. This four-quadrant classification generates engagement strategies: manage closely for high power and high interest stakeholders, keep satisfied for high power but lower interest stakeholders, keep informed for lower power but high interest stakeholders, and monitor for stakeholders with both lower power and lower interest. This framework provides strategic guidance beyond treating all stakeholders identically.

Mapping enables pattern recognition revealing stakeholder coalitions, potential conflicts, communication networks, and influence paths that aren’t apparent from stakeholder lists. Visual representation shows relationships and clusters helping project managers understand political dynamics and informal influence structures. This systemic stakeholder understanding enables sophisticated engagement strategies that work with organizational realities rather than ignoring them. Regular map updates track changing stakeholder positions and relationships maintaining current understanding throughout project lifecycles.

Question 119

What is the purpose of parametric estimating?

A) To guess project costs randomly 

B) To use statistical relationships between historical data and variables to estimate costs or durations 

C) To always overestimate project costs 

D) To eliminate the need for project planning

Answer: B) To use statistical relationships between historical data and variables to estimate costs or durations

Explanation: 

Parametric estimating uses statistical relationships between historical data and project variables to calculate cost or duration estimates based on project parameters. This technique applies mathematical models correlating characteristics like size, quantity, or complexity with costs or durations producing estimates more accurate than analogous estimating while requiring less detail than bottom-up estimating. Parametric estimating balances accuracy, effort, and speed making it valuable throughout project lifecycles.

Cost or duration parameters might include square footage for construction, lines of code for software, circuit miles for telecommunications, or user count for systems. Historical data establishes relationships between these parameters and project outcomes. For example, if historical data shows buildings cost $150 per square foot, a 10,000 square foot building is estimated at $1.5 million. More sophisticated models might adjust base rates for complexity, location, or other variables improving estimate accuracy through multi-variable relationships.

Model validity depends on accurate historical data and appropriate similarity between historical and current projects. If historical projects differ significantly in technology, team capability, or context, parametric relationships might not apply. Model calibration using organizational data produces better results than generic industry parameters because organizational factors affecting productivity and costs are reflected. Regular model updates incorporating recent project actuals maintain model accuracy as organizational capabilities and market conditions evolve.

Question 120

What is the purpose of reserve analysis in project management?

A) To eliminate all project risks 

B) To determine contingency and management reserves needed for cost and schedule uncertainty 

C) To increase project budgets unnecessarily 

D) To avoid project planning

Answer: B) To determine contingency and management reserves needed for cost and schedule uncertainty

Explanation: 

Reserve analysis determines the amount of contingency reserves for identified risks and management reserves for unknown risks that should be included in project budgets and schedules. This analysis acknowledges that projects face uncertainty that cannot be completely eliminated through planning and establishes appropriate buffers to absorb impacts without derailing projects. Reserve analysis transforms risk management from theoretical assessment to practical financial protection enabling realistic commitments that account for uncertainty.

Contingency reserves address known risks that have been identified and analyzed during risk management planning. The reserve amount is typically calculated based on risk exposure using expected monetary value, sensitivity analysis, or Monte Carlo simulation. These reserves belong to the project and can be used by the project manager when identified risks materialize according to predefined risk response plans. Contingency reserves recognize that despite mitigation efforts, some risks will materialize and require funding to address.

Management reserves address unknown risks that could not be identified during planning representing the general uncertainty inherent in projects. These reserves are held outside the cost baseline and require management approval for use because they address situations that weren’t anticipated during planning. The reserve amount typically relates to overall project risk exposure and organizational risk tolerance. Management reserves protect against the reality that risk identification never captures every possible problem that might occur during execution.

Reserve adequacy balances multiple considerations including project risk profile, organizational risk tolerance, strategic importance, and alternative risk response strategies. High-risk projects with low risk tolerance warrant larger reserves while low-risk projects with high tolerance might justify minimal reserves. Reserves represent organizational acknowledgment that perfection is impossible and that intelligent provision for uncertainty serves organizations better than unrealistic commitments assuming perfect execution and completely predictable conditions.

Leave a Reply

How It Works

img
Step 1. Choose Exam
on ExamLabs
Download IT Exams Questions & Answers
img
Step 2. Open Exam with
Avanset Exam Simulator
Press here to download VCE Exam Simulator that simulates real exam environment
img
Step 3. Study
& Pass
IT Exams Anywhere, Anytime!