Certified Information Security Manager CISM Practice Test 50
Question 490
Corrective-action owners exist, but investigators have not examined process and design causes beyond the operator. The response team proposes to investigate systemic governance, process and technical root causes. Who should have authority to approve this step under the relevant incident or continuity plan?
- The independent audit team because it later validates recovery effectiveness — using independent review duties as approval authority for root cause and corrective action.
- The accountable business process or control owner authorized to fund and accept remediation — for the decision to investigate systemic governance, process and technical root causes.
- The most senior system administrator because that person has the operational recovery credentials — using technical implementation responsibility as approval authority for root cause and corrective action.
- The external response provider because it can execute the technical work most quickly — using contractual delivery responsibility as approval authority for root cause and corrective action.
Explanation
Correct Answer
B:For root cause and corrective action, the named accountable authority can balance business, security and legal consequences under its delegated mandate. Specialist staff implement or advise; material deviations require escalation. The decision also addresses the risk that blaming an individual can leave systemic control failures uncorrected.
Incorrect Answers
A:Independent assurance should test and challenge the root cause and corrective action decision, not ordinarily authorize the activity it will later evaluate. That would blur accountability and separation of duties.
C:Access to technical systems does not automatically confer enterprise authority over root cause and corrective action. The operator may recommend or execute a properly authorized decision but cannot unilaterally accept the business consequences.
D:Contractual delivery responsibility and technical expertise do not transfer the enterprise’s ultimate accountability for root cause and corrective action. The responsible internal authority must approve consequential decisions.
Question 491
Management accepted corrective actions, but funded control improvements have not been deployed. What governance or response action addresses the stated gap?
- Revisit assessed exposure to investigate systemic governance, process and technical root causes.
- Prepare an effectiveness review to verify that improvements persist and escalate overdue corrective actions.
- Put the approved plan into operation to approve funded control improvements and risk decisions.
- Reconfirm delegated approval to assign accountable corrective action owners and independent oversight.
Explanation
Correct Answer
C:Approve funded control improvements and risk decisions. The scenario's unresolved need is implementation, and this action produces an implemented and tested treatment for root cause and corrective action. That directly addresses the risk that blaming an individual can leave systemic control failures uncorrected.
Incorrect Answers
A:Investigate systemic governance, process and technical root causes is pertinent to risk evaluation, but the scenario already assumes that prerequisite is established. Repeating it does not provide an implemented and tested treatment now needed for root cause and corrective action.
B:Verify that improvements persist and escalate overdue corrective actions is pertinent to control assurance, but it depends on a still-missing implementation decision or record. Applying it first would leave the current root cause and corrective action exposure unresolved, even if that later action is worthwhile.
D:Assign accountable corrective action owners and independent oversight is pertinent to delegated ownership, but the scenario already assumes that prerequisite is established. Repeating it does not provide an implemented and tested treatment now needed for root cause and corrective action.
Question 492
Management accepted corrective actions, but funded control improvements have not been deployed. A director recommends: "Verify that improvements persist and escalate overdue corrective actions." What response best addresses the evidence and decision authority in the case?
- Combine work to verify that improvements persist and escalate overdue corrective actions and assign accountable corrective action owners and independent oversight in a single funded milestone; document the decision to approve funded control improvements and risk decisions for later closure.
- Authorize a bounded pilot to verify that improvements persist and escalate overdue corrective actions, then use its results to determine whether the team still needs to approve funded control improvements and risk decisions.
- Begin with the alternative action to assign accountable corrective action owners and independent oversight and reassess whether the team still needs to approve funded control improvements and risk decisions after observing outcomes.
- Address the unmet requirement to approve funded control improvements and risk decisions, while separately coordinating urgent protective steps within approved authority.
Explanation
Correct Answer
D:This preserves the outstanding implementation decision without treating verify that improvements persist and escalate overdue corrective actions as inherently invalid. The immediate requirement is an implemented and tested treatment. Any urgent safety or containment action can continue if it is authorized under a separate response plan.
Incorrect Answers
A:Bundling treatment activities can be efficient, but funding two other actions does not show the named implementation gap is resolved. The present management decision still needs a responsible owner and supporting evidence.
B:The proposal to verify that improvements persist and escalate overdue corrective actions might be a useful pilot, but the case already identifies a missing implementation requirement. A pilot cannot replace an implemented and tested treatment; it should be assessed only within authorized boundaries.
C:Assign accountable corrective action owners and independent oversight can be useful in root cause and corrective action, but it does not eliminate the unmet requirement to approve funded control improvements and risk decisions. The proposed order risks assessing the wrong outcome or missing accountable authorization for the case.
Question 493
Management accepted corrective actions, but funded control improvements have not been deployed. What evidence would the risk committee need BEFORE it could close this finding?
- An accountable implementation sign-off and test result for the action to approve funded control improvements and risk decisions.
- A version-controlled delegation and escalation memo establishing the authority to assign accountable corrective action owners and independent oversight.
- A risk treatment justification with service impact evidence supporting the decision to investigate systemic governance, process and technical root causes.
- A control-performance review recording exceptions and corrections following work to verify that improvements persist and escalate overdue corrective actions.
Explanation
Correct Answer
A:An accountable implementation sign-off and test result for the action to approve funded control improvements and risk decisions. It specifically verifies an implemented and tested treatment, the outstanding requirement in this case. This matters because blaming an individual can leave systemic control failures uncorrected and an assertion of compliance alone cannot show that the risk has been managed.
Incorrect Answers
B:This would document earlier delegated ownership, which the case has already established. It does not demonstrate an implemented and tested treatment required to resolve the current issue.
C:This would document earlier risk evaluation, which the case has already established. It does not demonstrate an implemented and tested treatment required to resolve the current issue.
D:This demonstrates a later control assurance objective, but it cannot substitute for the unresolved implementation decision in the case. The evidence is valuable only when that prerequisite is met.
Question 494
A lessons-learned document is filed, yet corrective actions remain overdue with no effectiveness retest. An updated assessment raises concern that blaming an individual can leave systemic control failures uncorrected. Which response keeps the management decision current and accountable?
- Report delivery of the existing root cause and corrective action plan without reopening the previous risk assumptions.
- Have incident or continuity leadership reassess the new root cause and corrective action evidence and revise the decision to verify that improvements persist and escalate overdue corrective actions under the response plan.
- Continue the approved root cause and corrective action exception until its original expiry, keeping the existing acceptance decision.
- Let the delivery team revise the root cause and corrective action response immediately and seek management ratification afterward.
Explanation
Correct Answer
B:Incident and continuity decisions must reflect changed consequences: blaming an individual can leave systemic control failures uncorrected. The authorized response leader should reassess the condition, involve the relevant business, safety or legal specialists, and document why the revised decision to verify that improvements persist and escalate overdue corrective actions remains proportionate.
Incorrect Answers
A:Historical approvals and task counts do not show that the changed risk remains within tolerance. The new condition warrants a refreshed analysis and accountable response, not solely activity reporting.
C:An exception record is not a substitute for assessing the significance of the new evidence to root cause and corrective action. Earlier acceptance was conditional on facts that may no longer hold.
D:Urgent actions may be allowed within predelegated incident authority, but unilateral changes by implementers do not replace accountable reassessment and escalation when business impact changes.
Question 495
A lessons-learned document is filed, yet corrective actions remain overdue with no effectiveness retest. The committee needs evidence about root cause and corrective action. Which deliverable would address the identified deficiency most directly?
- A signed delegation and escalation record authorizing the organization to assign accountable corrective action owners and independent oversight for the operation needing effectiveness evidence.
- A management-endorsed assessment documenting the evidence needed to investigate systemic governance, process and technical root causes for the operation needing effectiveness evidence.
- An assurance review and corrective-action record confirming results from a decision to verify that improvements persist and escalate overdue corrective actions for the operation needing effectiveness evidence.
- A traceable deployment record and operating test confirming action to approve funded control improvements and risk decisions for the operation needing effectiveness evidence.
Explanation
Correct Answer
C:Verify that improvements persist and escalate overdue corrective actions. The scenario's unresolved need is control assurance, and this action produces monitoring evidence and accountable corrective actions for root cause and corrective action. That directly addresses the risk that blaming an individual can leave systemic control failures uncorrected.
Incorrect Answers
A:Assign accountable corrective action owners and independent oversight is pertinent to delegated ownership, but the scenario already assumes that prerequisite is established. Repeating it does not provide monitoring evidence and accountable corrective actions now needed for root cause and corrective action.
B:Investigate systemic governance, process and technical root causes is pertinent to risk evaluation, but the scenario already assumes that prerequisite is established. Repeating it does not provide monitoring evidence and accountable corrective actions now needed for root cause and corrective action.
D:Approve funded control improvements and risk decisions is pertinent to implementation, but the scenario already assumes that prerequisite is established. Repeating it does not provide monitoring evidence and accountable corrective actions now needed for root cause and corrective action.
Question 496
The alternate data center starts servers but users cannot log in, and no owner accepts end-to-end recovery responsibility. Which record would BEST show the immediate management deficiency has been resolved?
- Deployment and representative operating tests demonstrating the decision to integrate authentication links in orchestrated failover procedures was implemented.
- An assurance log of outcomes, exceptions and follow-up after the decision to verify real business transactions at the recovery site.
- A signed exposure and control assessment informing the decision to map network and identity dependencies and alternate-site capacity.
- An approved responsibility and delegation record authorizing the decision to assign end-to-end service recovery responsibility across infrastructure and identity.
Explanation
Correct Answer
D:An approved responsibility and delegation record authorizing the decision to assign end-to-end service recovery responsibility across infrastructure and identity. It specifically verifies an approved decision and escalation record, the outstanding requirement in this case. This matters because successfully started servers may still fail to perform transactions without identity dependencies and an assertion of compliance alone cannot show that the risk has been managed.
Incorrect Answers
A:This demonstrates a later implementation objective, but it cannot substitute for the unresolved delegated ownership decision in the case. The evidence is valuable only when that prerequisite is met.
B:This demonstrates a later control assurance objective, but it cannot substitute for the unresolved delegated ownership decision in the case. The evidence is valuable only when that prerequisite is met.
C:This demonstrates a later risk evaluation objective, but it cannot substitute for the unresolved delegated ownership decision in the case. The evidence is valuable only when that prerequisite is met.
Question 497
The alternate data center starts servers but users cannot log in, and no owner accepts end-to-end recovery responsibility. Which decision addresses the documented deficiency most directly?
- Assign end-to-end service recovery responsibility across infrastructure and identity.
- Verify real business transactions at the recovery site.
- Map network and identity dependencies and alternate-site capacity.
- Integrate authentication links in orchestrated failover procedures.
Explanation
Correct Answer
A:Assign end-to-end service recovery responsibility across infrastructure and identity. The scenario's unresolved need is delegated ownership, and this action produces an approved decision and escalation record for alternate site disaster recovery. That directly addresses the risk that successfully started servers may still fail to perform transactions without identity dependencies.
Incorrect Answers
B:Verify real business transactions at the recovery site is pertinent to control assurance, but it depends on a still-missing delegated ownership decision or record. Applying it first would leave the current alternate site disaster recovery exposure unresolved, even if that later action is worthwhile.
C:Map network and identity dependencies and alternate-site capacity is pertinent to risk evaluation, but it depends on a still-missing delegated ownership decision or record. Applying it first would leave the current alternate site disaster recovery exposure unresolved, even if that later action is worthwhile.
D:Integrate authentication links in orchestrated failover procedures is pertinent to implementation, but it depends on a still-missing delegated ownership decision or record. Applying it first would leave the current alternate site disaster recovery exposure unresolved, even if that later action is worthwhile.
Question 498
The alternate data center starts servers but users cannot log in, and no owner accepts end-to-end recovery responsibility. A director recommends: "Map network and identity dependencies and alternate-site capacity." What response best addresses the evidence and decision authority in the case?
- Authorize a bounded pilot to map network and identity dependencies and alternate-site capacity, then use its results to determine whether the team still needs to assign end-to-end service recovery responsibility across infrastructure and identity.
- Address the unmet requirement to assign end-to-end service recovery responsibility across infrastructure and identity, while separately coordinating urgent protective steps within approved authority.
- Begin with the alternative action to integrate authentication links in orchestrated failover procedures and reassess whether the team still needs to assign end-to-end service recovery responsibility across infrastructure and identity after observing outcomes.
- Combine work to map network and identity dependencies and alternate-site capacity and integrate authentication links in orchestrated failover procedures in a single funded milestone; document the decision to assign end-to-end service recovery responsibility across infrastructure and identity for later closure.
Explanation
Correct Answer
B:This preserves the outstanding delegated ownership decision without treating map network and identity dependencies and alternate-site capacity as inherently invalid. The immediate requirement is an approved decision and escalation record. Any urgent safety or containment action can continue if it is authorized under a separate response plan.
Incorrect Answers
A:The proposal to map network and identity dependencies and alternate-site capacity might be a useful pilot, but the case already identifies a missing delegated ownership requirement. A pilot cannot replace an approved decision and escalation record; it should be assessed only within authorized boundaries.
C:Integrate authentication links in orchestrated failover procedures can be useful in alternate site disaster recovery, but it does not eliminate the unmet requirement to assign end-to-end service recovery responsibility across infrastructure and identity. The proposed order risks assessing the wrong outcome or missing accountable authorization for the case.
D:Bundling treatment activities can be efficient, but funding two other actions does not show the named delegated ownership gap is resolved. The present management decision still needs a responsible owner and supporting evidence.
Question 499
Recovery ownership is assigned; identity and transaction dependencies across sites have not been mapped. The response team proposes to map network and identity dependencies and alternate-site capacity. Who should have authority to approve this step under the relevant incident or continuity plan?
- The independent audit team because it later validates recovery effectiveness — using independent review duties as approval authority for alternate site disaster recovery.
- The most senior system administrator because that person has the operational recovery credentials — using technical implementation responsibility as approval authority for alternate site disaster recovery.
- The accountable business recovery sponsor coordinating identity, network and application owners — for the decision to map network and identity dependencies and alternate-site capacity.
- The external response provider because it can execute the technical work most quickly — using contractual delivery responsibility as approval authority for alternate site disaster recovery.
Explanation
Correct Answer
C:For alternate site disaster recovery, the named accountable authority can balance business, security and legal consequences under its delegated mandate. Specialist staff implement or advise; material deviations require escalation. The decision also addresses the risk that successfully started servers may still fail to perform transactions without identity dependencies.
Incorrect Answers
A:Independent assurance should test and challenge the alternate site disaster recovery decision, not ordinarily authorize the activity it will later evaluate. That would blur accountability and separation of duties.
B:Access to technical systems does not automatically confer enterprise authority over alternate site disaster recovery. The operator may recommend or execute a properly authorized decision but cannot unilaterally accept the business consequences.
D:Contractual delivery responsibility and technical expertise do not transfer the enterprise’s ultimate accountability for alternate site disaster recovery. The responsible internal authority must approve consequential decisions.
Question 500
Recovery ownership is assigned; identity and transaction dependencies across sites have not been mapped. An updated assessment raises concern that successfully started servers may still fail to perform transactions without identity dependencies. Which response keeps the management decision current and accountable?
- Continue the approved alternate site disaster recovery exception until its original expiry, keeping the existing acceptance decision.
- Let the delivery team revise the alternate site disaster recovery response immediately and seek management ratification afterward.
- Report delivery of the existing alternate site disaster recovery plan without reopening the previous risk assumptions.
- Have incident or continuity leadership reassess the new alternate site disaster recovery evidence and revise the decision to map network and identity dependencies and alternate-site capacity under the response plan.
Explanation
Correct Answer
D:Incident and continuity decisions must reflect changed consequences: successfully started servers may still fail to perform transactions without identity dependencies. The authorized response leader should reassess the condition, involve the relevant business, safety or legal specialists, and document why the revised decision to map network and identity dependencies and alternate-site capacity remains proportionate.
Incorrect Answers
A:An exception record is not a substitute for assessing the significance of the new evidence to alternate site disaster recovery. Earlier acceptance was conditional on facts that may no longer hold.
B:Urgent actions may be allowed within predelegated incident authority, but unilateral changes by implementers do not replace accountable reassessment and escalation when business impact changes.
C:Historical approvals and task counts do not show that the changed risk remains within tolerance. The new condition warrants a refreshed analysis and accountable response, not solely activity reporting.