Question 450
At Fictional Orbital Commerce, the proposed AI governance implementation rollout is undergoing an ISO/IEC 42001 implementation review following an interrupted model release. The observed failure is: A treatment plan describes several unresolved high-impact AI risks but allows project developers to sign off on them without defined thresholds. The implementation may continue only after measurable evidence demonstrates the intended control outcome. Which proposed shortcut must be REJECTED because it weakens reliability, correctness, auditability, or access control?
- For Fictional Orbital Commerce while preserving approved oversight, revisit high residual risks at set intervals and when incident or model evidence changes.
- For Fictional Orbital Commerce while preserving approved oversight, define risk acceptance levels and named approvers, escalate exceptions, and record rationale plus conditions for accepted exposure.
- For Fictional Orbital Commerce while preserving approved oversight, let the delivery team approve its own unmitigated high-consequence risks by changing a spreadsheet status.
- For Fictional Orbital Commerce while preserving approved oversight, each above-threshold residual risk has a documented decision from the proper authority and evidence of required compensating controls.
Explanation
Correct Answer
C:Do not let the delivery team approve its own unmitigated high-consequence risks by changing a spreadsheet status. Residual risk is a governance decision that requires authorized acceptance criteria and independent escalation where risk exceeds delegated limits. Define risk acceptance levels and named approvers, escalate exceptions, and record rationale plus conditions for accepted exposure. Each above-threshold residual risk has a documented decision from the proper authority and evidence of required compensating controls.
Incorrect Answers
A:Revisit high residual risks at set intervals and when incident or model evidence changes. This is a preventive operational safeguard that reduces recurrence because residual risk is a governance decision that requires authorized acceptance criteria and independent escalation where risk exceeds delegated limits. It should be retained. The unsafe proposal is let the delivery team approve its own unmitigated high-consequence risks by changing a spreadsheet status.
B:Define risk acceptance levels and named approvers, escalate exceptions, and record rationale plus conditions for accepted exposure. This is the controlled remediation, not the unsafe shortcut. It addresses residual risk is a governance decision that requires authorized acceptance criteria and independent escalation where risk exceeds delegated limits. The unsafe step is to let the delivery team approve its own unmitigated high-consequence risks by changing a spreadsheet status.
D:Each above-threshold residual risk has a documented decision from the proper authority and evidence of required compensating controls. This is measurable acceptance evidence rather than a risky change. It provides evidence that the scoped remediation was successful: Define risk acceptance levels and named approvers, escalate exceptions, and record rationale plus conditions for accepted exposure. The unsafe step is to let the delivery team approve its own unmitigated high-consequence risks by changing a spreadsheet status.
Question 451
At Fictional Terra University, the AIMS project charter and readiness assessment is undergoing an ISO/IEC 42001 implementation review while a new geographic market is onboarded. The observed failure is: A planned AIMS implementation cannot proceed after a key governance specialist leaves, and no fallback for the required approval work exists. The proposed remedy must remain scoped, traceable, and verifiable without changing unrelated processes. Which scoped implementation action should the AIMS lead take first?
- For Fictional Terra University under the scoped AI governance decision, draft and approve a charter with sponsor, boundaries, objectives, milestones, decision rights, dependencies, and success measures.
- For Fictional Terra University under the scoped AI governance decision, identify key-person dependencies, assign deputies, reserve schedule buffers, and define escalation and re-baselining triggers.
- For Fictional Terra University under the scoped AI governance decision, map affected parties and applicable obligations with legal, business, customer, and operational representatives before approving the AIMS plan.
- For Fictional Terra University under the scoped AI governance decision, present resource and capacity needs to top management, obtain sponsorship, and fund critical risk and implementation activities.
Explanation
Correct Answer
B:Identify key-person dependencies, assign deputies, reserve schedule buffers, and define escalation and re-baselining triggers. A program plan must manage delivery risks and dependencies so critical implementation controls are not silently skipped under pressure. A simulated staffing gap is resolved through an approved alternate reviewer without dropping mandatory risk approvals.
Incorrect Answers
A:Draft and approve a charter with sponsor, boundaries, objectives, milestones, decision rights, dependencies, and success measures. A governance implementation program needs an explicit charter so stakeholders can distinguish authorized scope and success criteria from unbounded aspirations. A planned AIMS implementation cannot proceed after a key governance specialist leaves, and no fallback for the required approval work exists. Identify key-person dependencies, assign deputies, reserve schedule buffers, and define escalation and re-baselining triggers.
C:Map affected parties and applicable obligations with legal, business, customer, and operational representatives before approving the AIMS plan. AIMS planning requires knowledge of relevant interested parties and their requirements; a technical-only perspective misses consequential obligations. A planned AIMS implementation cannot proceed after a key governance specialist leaves, and no fallback for the required approval work exists. Identify key-person dependencies, assign deputies, reserve schedule buffers, and define escalation and re-baselining triggers.
D:Present resource and capacity needs to top management, obtain sponsorship, and fund critical risk and implementation activities. AIMS delivery depends on leadership authority and realistic resources, not solely on a policy statement. A planned AIMS implementation cannot proceed after a key governance specialist leaves, and no fallback for the required approval work exists. Identify key-person dependencies, assign deputies, reserve schedule buffers, and define escalation and re-baselining triggers.
Question 452
At Fictional Terra University, the AIMS project charter and readiness assessment is undergoing an ISO/IEC 42001 implementation review while a new geographic market is onboarded. The observed failure is: A planned AIMS implementation cannot proceed after a key governance specialist leaves, and no fallback for the required approval work exists. The proposed remedy must remain scoped, traceable, and verifiable without changing unrelated processes. Which underlying mechanism best explains these symptoms?
- For Fictional Terra University under the scoped AI governance decision, AI risk assessments should address relevant harms and opportunities in context rather than equating all AI risk with information security.
- For Fictional Terra University under the scoped AI governance decision, residual risk is a governance decision that requires authorized acceptance criteria and independent escalation where risk exceeds delegated limits.
- For Fictional Terra University under the scoped AI governance decision, a program plan must manage delivery risks and dependencies so critical implementation controls are not silently skipped under pressure.
- For Fictional Terra University under the scoped AI governance decision, diffuse accountability creates control gaps unless responsibilities and approval rights are unambiguous for each decision.
Explanation
Correct Answer
C:A program plan must manage delivery risks and dependencies so critical implementation controls are not silently skipped under pressure. Identify key-person dependencies, assign deputies, reserve schedule buffers, and define escalation and re-baselining triggers. A simulated staffing gap is resolved through an approved alternate reviewer without dropping mandatory risk approvals.
Incorrect Answers
A:AI risk assessments should address relevant harms and opportunities in context rather than equating all AI risk with information security. A planned AIMS implementation cannot proceed after a key governance specialist leaves, and no fallback for the required approval work exists. A program plan must manage delivery risks and dependencies so critical implementation controls are not silently skipped under pressure.
B:Residual risk is a governance decision that requires authorized acceptance criteria and independent escalation where risk exceeds delegated limits. A planned AIMS implementation cannot proceed after a key governance specialist leaves, and no fallback for the required approval work exists. A program plan must manage delivery risks and dependencies so critical implementation controls are not silently skipped under pressure.
D:Diffuse accountability creates control gaps unless responsibilities and approval rights are unambiguous for each decision. A planned AIMS implementation cannot proceed after a key governance specialist leaves, and no fallback for the required approval work exists. A program plan must manage delivery risks and dependencies so critical implementation controls are not silently skipped under pressure.
Question 453
At Fictional Terra University, the AIMS project charter and readiness assessment is undergoing an ISO/IEC 42001 implementation review while a new geographic market is onboarded. The observed failure is: A planned AIMS implementation cannot proceed after a key governance specialist leaves, and no fallback for the required approval work exists. The proposed remedy must remain scoped, traceable, and verifiable without changing unrelated processes. Which observable acceptance test most directly shows that this defect is fixed?
- For Fictional Terra University under the scoped AI governance decision, a simulated staffing gap is resolved through an approved alternate reviewer without dropping mandatory risk approvals.
- For Fictional Terra University under the scoped AI governance decision, the assessment documents representative AI-specific harms, likelihood/consequence reasoning, control owners, and residual exposure.
- For Fictional Terra University under the scoped AI governance decision, the signed charter names accountable sponsors, major deliverables, approved resources, and criteria for moving between phases.
- For Fictional Terra University under the scoped AI governance decision, sampled shared models have documented responsible owners and verifiable controls on both sides of the declared boundary.
Explanation
Correct Answer
A:A simulated staffing gap is resolved through an approved alternate reviewer without dropping mandatory risk approvals. A program plan must manage delivery risks and dependencies so critical implementation controls are not silently skipped under pressure. Identify key-person dependencies, assign deputies, reserve schedule buffers, and define escalation and re-baselining triggers.
Incorrect Answers
B:The assessment documents representative AI-specific harms, likelihood/consequence reasoning, control owners, and residual exposure. Evidence for aI risk assessment completeness concerns a different issue. A simulated staffing gap is resolved through an approved alternate reviewer without dropping mandatory risk approvals.
C:The signed charter names accountable sponsors, major deliverables, approved resources, and criteria for moving between phases. Evidence for aIMS implementation charter concerns a different issue. A simulated staffing gap is resolved through an approved alternate reviewer without dropping mandatory risk approvals.
D:Sampled shared models have documented responsible owners and verifiable controls on both sides of the declared boundary. Evidence for aIMS program boundary design concerns a different issue. A simulated staffing gap is resolved through an approved alternate reviewer without dropping mandatory risk approvals.
Question 454
At Fictional Terra University, the AIMS project charter and readiness assessment is undergoing an ISO/IEC 42001 implementation review while a new geographic market is onboarded. The observed failure is: A planned AIMS implementation cannot proceed after a key governance specialist leaves, and no fallback for the required approval work exists. The proposed remedy must remain scoped, traceable, and verifiable without changing unrelated processes. Which recurring safeguard best prevents this specific failure from recurring?
- For Fictional Terra University under the scoped AI governance decision, reforecast staffing and budget at each stage gate and escalate material shortfalls.
- For Fictional Terra University under the scoped AI governance decision, reassess delivery contingencies and critical-path assumptions during program checkpoints.
- For Fictional Terra University under the scoped AI governance decision, reassess impacts when deployment scale, population, or downstream decision effect changes.
- For Fictional Terra University under the scoped AI governance decision, maintain the charter through formal change control and review it at major milestones.
Explanation
Correct Answer
B:Reassess delivery contingencies and critical-path assumptions during program checkpoints. A program plan must manage delivery risks and dependencies so critical implementation controls are not silently skipped under pressure. A simulated staffing gap is resolved through an approved alternate reviewer without dropping mandatory risk approvals.
Incorrect Answers
A:Reforecast staffing and budget at each stage gate and escalate material shortfalls. Leadership resources and sponsorship is a separate risk. A program plan must manage delivery risks and dependencies so critical implementation controls are not silently skipped under pressure. Reassess delivery contingencies and critical-path assumptions during program checkpoints.
C:Reassess impacts when deployment scale, population, or downstream decision effect changes. AI system impact assessment plan is a separate risk. A program plan must manage delivery risks and dependencies so critical implementation controls are not silently skipped under pressure. Reassess delivery contingencies and critical-path assumptions during program checkpoints.
D:Maintain the charter through formal change control and review it at major milestones. AIMS implementation charter is a separate risk. A program plan must manage delivery risks and dependencies so critical implementation controls are not silently skipped under pressure. Reassess delivery contingencies and critical-path assumptions during program checkpoints.
Question 455
At Fictional Terra University, the AIMS project charter and readiness assessment is undergoing an ISO/IEC 42001 implementation review while a new geographic market is onboarded. The observed failure is: A planned AIMS implementation cannot proceed after a key governance specialist leaves, and no fallback for the required approval work exists. The proposed remedy must remain scoped, traceable, and verifiable without changing unrelated processes. Which proposed shortcut must be REJECTED because it weakens reliability, correctness, auditability, or access control?
- For Fictional Terra University under the scoped AI governance decision, a simulated staffing gap is resolved through an approved alternate reviewer without dropping mandatory risk approvals.
- For Fictional Terra University under the scoped AI governance decision, identify key-person dependencies, assign deputies, reserve schedule buffers, and define escalation and re-baselining triggers.
- For Fictional Terra University under the scoped AI governance decision, remove required assessment work from the schedule whenever an owner is unavailable.
- For Fictional Terra University under the scoped AI governance decision, reassess delivery contingencies and critical-path assumptions during program checkpoints.
Explanation
Correct Answer
C:Do not remove required assessment work from the schedule whenever an owner is unavailable. A program plan must manage delivery risks and dependencies so critical implementation controls are not silently skipped under pressure. Identify key-person dependencies, assign deputies, reserve schedule buffers, and define escalation and re-baselining triggers. A simulated staffing gap is resolved through an approved alternate reviewer without dropping mandatory risk approvals.
Incorrect Answers
A:A simulated staffing gap is resolved through an approved alternate reviewer without dropping mandatory risk approvals. This is measurable acceptance evidence rather than a risky change. It provides evidence that the scoped remediation was successful: Identify key-person dependencies, assign deputies, reserve schedule buffers, and define escalation and re-baselining triggers. The unsafe step is to remove required assessment work from the schedule whenever an owner is unavailable.
B:Identify key-person dependencies, assign deputies, reserve schedule buffers, and define escalation and re-baselining triggers. This is the controlled remediation, not the unsafe shortcut. It addresses a program plan must manage delivery risks and dependencies so critical implementation controls are not silently skipped under pressure. The unsafe step is to remove required assessment work from the schedule whenever an owner is unavailable.
D:Reassess delivery contingencies and critical-path assumptions during program checkpoints. This is a preventive operational safeguard that reduces recurrence because a program plan must manage delivery risks and dependencies so critical implementation controls are not silently skipped under pressure. It should be retained. The unsafe proposal is remove required assessment work from the schedule whenever an owner is unavailable.
Question 456
At Fictional Ember Games, the corporate AI risks and controls planning process is undergoing an ISO/IEC 42001 implementation review in a controlled AI service transition. The observed failure is: A planned AIMS implementation cannot proceed after a key governance specialist leaves, and no fallback for the required approval work exists. Affected users and existing AI services must remain protected while the team verifies the governance correction. Which scoped implementation action should the AIMS lead take first?
- For Fictional Ember Games while preserving approved oversight, estimate roles, skills, tools, evidence costs, and recurring operational capacity in a phased resource plan.
- For Fictional Ember Games while preserving approved oversight, reassess the decision impact, document a defensible applicability determination, and include oversight where the identified risks warrant it.
- For Fictional Ember Games while preserving approved oversight, derive control applicability from risk treatment decisions, record inclusion or exclusion justifications, and track implementation evidence.
- For Fictional Ember Games while preserving approved oversight, identify key-person dependencies, assign deputies, reserve schedule buffers, and define escalation and re-baselining triggers.
Explanation
Correct Answer
D:Identify key-person dependencies, assign deputies, reserve schedule buffers, and define escalation and re-baselining triggers. A program plan must manage delivery risks and dependencies so critical implementation controls are not silently skipped under pressure. A simulated staffing gap is resolved through an approved alternate reviewer without dropping mandatory risk approvals.
Incorrect Answers
A:Estimate roles, skills, tools, evidence costs, and recurring operational capacity in a phased resource plan. AIMS implementation resources extend beyond software build work to governance, human capability, measurement, and long-term maintenance. A planned AIMS implementation cannot proceed after a key governance specialist leaves, and no fallback for the required approval work exists. Identify key-person dependencies, assign deputies, reserve schedule buffers, and define escalation and re-baselining triggers.
B:Reassess the decision impact, document a defensible applicability determination, and include oversight where the identified risks warrant it. Whether a control is needed depends on actual purpose and risk; a superficial internal-use label cannot justify every exclusion. A planned AIMS implementation cannot proceed after a key governance specialist leaves, and no fallback for the required approval work exists. Identify key-person dependencies, assign deputies, reserve schedule buffers, and define escalation and re-baselining triggers.
C:Derive control applicability from risk treatment decisions, record inclusion or exclusion justifications, and track implementation evidence. A Statement of Applicability needs reasoned control selection and implementation status linked to risk treatment, not a pasted control inventory. A planned AIMS implementation cannot proceed after a key governance specialist leaves, and no fallback for the required approval work exists. Identify key-person dependencies, assign deputies, reserve schedule buffers, and define escalation and re-baselining triggers.
Question 457
At Fictional Ember Games, the corporate AI risks and controls planning process is undergoing an ISO/IEC 42001 implementation review in a controlled AI service transition. The observed failure is: A planned AIMS implementation cannot proceed after a key governance specialist leaves, and no fallback for the required approval work exists. Affected users and existing AI services must remain protected while the team verifies the governance correction. Which underlying mechanism best explains these symptoms?
- For Fictional Ember Games while preserving approved oversight, AIMS planning must align intended AI operation with approved organizational policy and applicable obligations.
- For Fictional Ember Games while preserving approved oversight, a program plan must manage delivery risks and dependencies so critical implementation controls are not silently skipped under pressure.
- For Fictional Ember Games while preserving approved oversight, AIMS planning requires knowledge of relevant interested parties and their requirements; a technical-only perspective misses consequential obligations.
- For Fictional Ember Games while preserving approved oversight, AIMS delivery depends on leadership authority and realistic resources, not solely on a policy statement.
Explanation
Correct Answer
B:A program plan must manage delivery risks and dependencies so critical implementation controls are not silently skipped under pressure. Identify key-person dependencies, assign deputies, reserve schedule buffers, and define escalation and re-baselining triggers. A simulated staffing gap is resolved through an approved alternate reviewer without dropping mandatory risk approvals.
Incorrect Answers
A:AIMS planning must align intended AI operation with approved organizational policy and applicable obligations. A planned AIMS implementation cannot proceed after a key governance specialist leaves, and no fallback for the required approval work exists. A program plan must manage delivery risks and dependencies so critical implementation controls are not silently skipped under pressure.
C:AIMS planning requires knowledge of relevant interested parties and their requirements; a technical-only perspective misses consequential obligations. A planned AIMS implementation cannot proceed after a key governance specialist leaves, and no fallback for the required approval work exists. A program plan must manage delivery risks and dependencies so critical implementation controls are not silently skipped under pressure.
D:AIMS delivery depends on leadership authority and realistic resources, not solely on a policy statement. A planned AIMS implementation cannot proceed after a key governance specialist leaves, and no fallback for the required approval work exists. A program plan must manage delivery risks and dependencies so critical implementation controls are not silently skipped under pressure.
Question 458
At Fictional Ember Games, the corporate AI risks and controls planning process is undergoing an ISO/IEC 42001 implementation review in a controlled AI service transition. The observed failure is: A planned AIMS implementation cannot proceed after a key governance specialist leaves, and no fallback for the required approval work exists. Affected users and existing AI services must remain protected while the team verifies the governance correction. Which observable acceptance test most directly shows that this defect is fixed?
- For Fictional Ember Games while preserving approved oversight, the stakeholder register shows relevant concerns, owners, obligations, and how they influence planned AI controls.
- For Fictional Ember Games while preserving approved oversight, a simulated high-impact release reaches the designated approver and produces one traceable decision rather than conflicting signatures.
- For Fictional Ember Games while preserving approved oversight, a simulated staffing gap is resolved through an approved alternate reviewer without dropping mandatory risk approvals.
- For Fictional Ember Games while preserving approved oversight, the project plan links funded roles and capacity to priority risks, deliverables, and documented executive approvals.
Explanation
Correct Answer
C:A simulated staffing gap is resolved through an approved alternate reviewer without dropping mandatory risk approvals. A program plan must manage delivery risks and dependencies so critical implementation controls are not silently skipped under pressure. Identify key-person dependencies, assign deputies, reserve schedule buffers, and define escalation and re-baselining triggers.
Incorrect Answers
A:The stakeholder register shows relevant concerns, owners, obligations, and how they influence planned AI controls. Evidence for interested-party requirements mapping concerns a different issue. A simulated staffing gap is resolved through an approved alternate reviewer without dropping mandatory risk approvals.
B:A simulated high-impact release reaches the designated approver and produces one traceable decision rather than conflicting signatures. Evidence for cross-functional accountability matrix concerns a different issue. A simulated staffing gap is resolved through an approved alternate reviewer without dropping mandatory risk approvals.
D:The project plan links funded roles and capacity to priority risks, deliverables, and documented executive approvals. Evidence for leadership resources and sponsorship concerns a different issue. A simulated staffing gap is resolved through an approved alternate reviewer without dropping mandatory risk approvals.
Question 459
At Fictional Ember Games, the corporate AI risks and controls planning process is undergoing an ISO/IEC 42001 implementation review in a controlled AI service transition. The observed failure is: A planned AIMS implementation cannot proceed after a key governance specialist leaves, and no fallback for the required approval work exists. Affected users and existing AI services must remain protected while the team verifies the governance correction. Which recurring safeguard best prevents this specific failure from recurring?
- For Fictional Ember Games while preserving approved oversight, exercise important supplier continuity paths and review contract terms after service changes.
- For Fictional Ember Games while preserving approved oversight, refresh the stakeholder map after regulatory, contractual, market, and AI-use changes.
- For Fictional Ember Games while preserving approved oversight, revalidate roles after reorganizations, outsourcing changes, and new AI deployment classes.
- For Fictional Ember Games while preserving approved oversight, reassess delivery contingencies and critical-path assumptions during program checkpoints.
Explanation
Correct Answer
D:Reassess delivery contingencies and critical-path assumptions during program checkpoints. A program plan must manage delivery risks and dependencies so critical implementation controls are not silently skipped under pressure. A simulated staffing gap is resolved through an approved alternate reviewer without dropping mandatory risk approvals.
Incorrect Answers
A:Exercise important supplier continuity paths and review contract terms after service changes. Cloud AI supplier dependency planning is a separate risk. A program plan must manage delivery risks and dependencies so critical implementation controls are not silently skipped under pressure. Reassess delivery contingencies and critical-path assumptions during program checkpoints.
B:Refresh the stakeholder map after regulatory, contractual, market, and AI-use changes. Interested-party requirements mapping is a separate risk. A program plan must manage delivery risks and dependencies so critical implementation controls are not silently skipped under pressure. Reassess delivery contingencies and critical-path assumptions during program checkpoints.
C:Revalidate roles after reorganizations, outsourcing changes, and new AI deployment classes. Cross-functional accountability matrix is a separate risk. A program plan must manage delivery risks and dependencies so critical implementation controls are not silently skipped under pressure. Reassess delivery contingencies and critical-path assumptions during program checkpoints.
Question 460
At Fictional Ember Games, the corporate AI risks and controls planning process is undergoing an ISO/IEC 42001 implementation review in a controlled AI service transition. The observed failure is: A planned AIMS implementation cannot proceed after a key governance specialist leaves, and no fallback for the required approval work exists. Affected users and existing AI services must remain protected while the team verifies the governance correction. Which proposed shortcut must be REJECTED because it weakens reliability, correctness, auditability, or access control?
- For Fictional Ember Games while preserving approved oversight, remove required assessment work from the schedule whenever an owner is unavailable.
- For Fictional Ember Games while preserving approved oversight, reassess delivery contingencies and critical-path assumptions during program checkpoints.
- For Fictional Ember Games while preserving approved oversight, identify key-person dependencies, assign deputies, reserve schedule buffers, and define escalation and re-baselining triggers.
- For Fictional Ember Games while preserving approved oversight, a simulated staffing gap is resolved through an approved alternate reviewer without dropping mandatory risk approvals.
Explanation
Correct Answer
A:Do not remove required assessment work from the schedule whenever an owner is unavailable. A program plan must manage delivery risks and dependencies so critical implementation controls are not silently skipped under pressure. Identify key-person dependencies, assign deputies, reserve schedule buffers, and define escalation and re-baselining triggers. A simulated staffing gap is resolved through an approved alternate reviewer without dropping mandatory risk approvals.
Incorrect Answers
B:Reassess delivery contingencies and critical-path assumptions during program checkpoints. This is a preventive operational safeguard that reduces recurrence because a program plan must manage delivery risks and dependencies so critical implementation controls are not silently skipped under pressure. It should be retained. The unsafe proposal is remove required assessment work from the schedule whenever an owner is unavailable.
C:Identify key-person dependencies, assign deputies, reserve schedule buffers, and define escalation and re-baselining triggers. This is the controlled remediation, not the unsafe shortcut. It addresses a program plan must manage delivery risks and dependencies so critical implementation controls are not silently skipped under pressure. The unsafe step is to remove required assessment work from the schedule whenever an owner is unavailable.
D:A simulated staffing gap is resolved through an approved alternate reviewer without dropping mandatory risk approvals. This is measurable acceptance evidence rather than a risky change. It provides evidence that the scoped remediation was successful: Identify key-person dependencies, assign deputies, reserve schedule buffers, and define escalation and re-baselining triggers. The unsafe step is to remove required assessment work from the schedule whenever an owner is unavailable.