Question 380
At Fictional Seabright Labs, the corporate AI risks and controls planning process is undergoing an ISO/IEC 42001 implementation review while a new geographic market is onboarded. The observed failure is: A program has a risk register but no method to document consequences of AI use for individuals, communities, and business stakeholders. The responsible owner must preserve the prior approved state and avoid unnecessary access or policy changes. Which proposed shortcut must be REJECTED because it weakens reliability, correctness, auditability, or access control?
- For Fictional Seabright Labs while preserving approved oversight, define impact-assessment triggers, relevant stakeholders, assessment steps, documentation, and review points within the AIMS plan.
- For Fictional Seabright Labs while preserving approved oversight, substitute a generic cybersecurity risk score for an AI impact assessment without considering affected people.
- For Fictional Seabright Labs while preserving approved oversight, reassess impacts when deployment scale, population, or downstream decision effect changes.
- For Fictional Seabright Labs while preserving approved oversight, a high-impact pilot has a completed and approved impact assessment with mitigations and an accountable reviewer.
Explanation
Correct Answer
B:Do not substitute a generic cybersecurity risk score for an AI impact assessment without considering affected people. An AI system impact assessment complements risk treatment by examining potential impacts in the specific use context and documenting decisions. Define impact-assessment triggers, relevant stakeholders, assessment steps, documentation, and review points within the AIMS plan. A high-impact pilot has a completed and approved impact assessment with mitigations and an accountable reviewer.
Incorrect Answers
A:Define impact-assessment triggers, relevant stakeholders, assessment steps, documentation, and review points within the AIMS plan. This is the controlled remediation, not the unsafe shortcut. It addresses an AI system impact assessment complements risk treatment by examining potential impacts in the specific use context and documenting decisions. The unsafe step is to substitute a generic cybersecurity risk score for an AI impact assessment without considering affected people.
C:Reassess impacts when deployment scale, population, or downstream decision effect changes. This is a preventive operational safeguard that reduces recurrence because an AI system impact assessment complements risk treatment by examining potential impacts in the specific use context and documenting decisions. It should be retained. The unsafe proposal is substitute a generic cybersecurity risk score for an AI impact assessment without considering affected people.
D:A high-impact pilot has a completed and approved impact assessment with mitigations and an accountable reviewer. This is measurable acceptance evidence rather than a risky change. It provides evidence that the scoped remediation was successful: Define impact-assessment triggers, relevant stakeholders, assessment steps, documentation, and review points within the AIMS plan. The unsafe step is to substitute a generic cybersecurity risk score for an AI impact assessment without considering affected people.
Question 381
At Fictional Compass Logistics, the proposed AI governance implementation rollout is undergoing an ISO/IEC 42001 implementation review before a material expansion of AI use. The observed failure is: A deployment timeline allocates engineers for model launch but omits reviewers, operator training, logging, impact assessment, and recurring monitoring. A controlled correction and repeatable evidence are required before wider AIMS rollout. Which scoped implementation action should the AIMS lead take first?
- For Fictional Compass Logistics under the scoped AI governance decision, estimate roles, skills, tools, evidence costs, and recurring operational capacity in a phased resource plan.
- For Fictional Compass Logistics under the scoped AI governance decision, define impact-assessment triggers, relevant stakeholders, assessment steps, documentation, and review points within the AIMS plan.
- For Fictional Compass Logistics under the scoped AI governance decision, compare applicable avoidance, modification, sharing, and acceptance decisions; select context-specific controls with responsible owners.
- For Fictional Compass Logistics under the scoped AI governance decision, group sites by risk and readiness, define local adaptations and staged gates, and pilot controls before scaling to other regions.
Explanation
Correct Answer
A:Estimate roles, skills, tools, evidence costs, and recurring operational capacity in a phased resource plan. AIMS implementation resources extend beyond software build work to governance, human capability, measurement, and long-term maintenance. The resource plan names owners and funded effort for each major AIMS activity, including post-launch monitoring.
Incorrect Answers
B:Define impact-assessment triggers, relevant stakeholders, assessment steps, documentation, and review points within the AIMS plan. An AI system impact assessment complements risk treatment by examining potential impacts in the specific use context and documenting decisions. A deployment timeline allocates engineers for model launch but omits reviewers, operator training, logging, impact assessment, and recurring monitoring. Estimate roles, skills, tools, evidence costs, and recurring operational capacity in a phased resource plan.
C:Compare applicable avoidance, modification, sharing, and acceptance decisions; select context-specific controls with responsible owners. Different risk mechanisms demand proportionate treatment and justified control choices rather than uniform implementation for appearance. A deployment timeline allocates engineers for model launch but omits reviewers, operator training, logging, impact assessment, and recurring monitoring. Estimate roles, skills, tools, evidence costs, and recurring operational capacity in a phased resource plan.
D:Group sites by risk and readiness, define local adaptations and staged gates, and pilot controls before scaling to other regions. Phased implementation allows local requirements and control readiness to be verified without assuming every site has the same risk and capacity. A deployment timeline allocates engineers for model launch but omits reviewers, operator training, logging, impact assessment, and recurring monitoring. Estimate roles, skills, tools, evidence costs, and recurring operational capacity in a phased resource plan.
Question 382
At Fictional Compass Logistics, the proposed AI governance implementation rollout is undergoing an ISO/IEC 42001 implementation review before a material expansion of AI use. The observed failure is: A deployment timeline allocates engineers for model launch but omits reviewers, operator training, logging, impact assessment, and recurring monitoring. A controlled correction and repeatable evidence are required before wider AIMS rollout. Which underlying mechanism best explains these symptoms?
- For Fictional Compass Logistics under the scoped AI governance decision, external AI dependencies can affect service continuity, risk response, and audit evidence even when procurement manages the commercial relationship.
- For Fictional Compass Logistics under the scoped AI governance decision, phased implementation allows local requirements and control readiness to be verified without assuming every site has the same risk and capacity.
- For Fictional Compass Logistics under the scoped AI governance decision, AIMS implementation resources extend beyond software build work to governance, human capability, measurement, and long-term maintenance.
- For Fictional Compass Logistics under the scoped AI governance decision, an AI system impact assessment complements risk treatment by examining potential impacts in the specific use context and documenting decisions.
Explanation
Correct Answer
C:AIMS implementation resources extend beyond software build work to governance, human capability, measurement, and long-term maintenance. Estimate roles, skills, tools, evidence costs, and recurring operational capacity in a phased resource plan. The resource plan names owners and funded effort for each major AIMS activity, including post-launch monitoring.
Incorrect Answers
A:External AI dependencies can affect service continuity, risk response, and audit evidence even when procurement manages the commercial relationship. A deployment timeline allocates engineers for model launch but omits reviewers, operator training, logging, impact assessment, and recurring monitoring. AIMS implementation resources extend beyond software build work to governance, human capability, measurement, and long-term maintenance.
B:Phased implementation allows local requirements and control readiness to be verified without assuming every site has the same risk and capacity. A deployment timeline allocates engineers for model launch but omits reviewers, operator training, logging, impact assessment, and recurring monitoring. AIMS implementation resources extend beyond software build work to governance, human capability, measurement, and long-term maintenance.
D:An AI system impact assessment complements risk treatment by examining potential impacts in the specific use context and documenting decisions. A deployment timeline allocates engineers for model launch but omits reviewers, operator training, logging, impact assessment, and recurring monitoring. AIMS implementation resources extend beyond software build work to governance, human capability, measurement, and long-term maintenance.
Question 383
At Fictional Compass Logistics, the proposed AI governance implementation rollout is undergoing an ISO/IEC 42001 implementation review before a material expansion of AI use. The observed failure is: A deployment timeline allocates engineers for model launch but omits reviewers, operator training, logging, impact assessment, and recurring monitoring. A controlled correction and repeatable evidence are required before wider AIMS rollout. Which observable acceptance test most directly shows that this defect is fixed?
- For Fictional Compass Logistics under the scoped AI governance decision, the resource plan names owners and funded effort for each major AIMS activity, including post-launch monitoring.
- For Fictional Compass Logistics under the scoped AI governance decision, a simulated high-impact release reaches the designated approver and produces one traceable decision rather than conflicting signatures.
- For Fictional Compass Logistics under the scoped AI governance decision, a chosen use case traces from its business purpose to supplier dependencies, data flows, owners, and intended control decisions.
- For Fictional Compass Logistics under the scoped AI governance decision, a sample Annex A control has an auditable applicability rationale, associated risk treatment, owner, and current implementation status.
Explanation
Correct Answer
A:The resource plan names owners and funded effort for each major AIMS activity, including post-launch monitoring. AIMS implementation resources extend beyond software build work to governance, human capability, measurement, and long-term maintenance. Estimate roles, skills, tools, evidence costs, and recurring operational capacity in a phased resource plan.
Incorrect Answers
B:A simulated high-impact release reaches the designated approver and produces one traceable decision rather than conflicting signatures. Evidence for cross-functional accountability matrix concerns a different issue. The resource plan names owners and funded effort for each major AIMS activity, including post-launch monitoring.
C:A chosen use case traces from its business purpose to supplier dependencies, data flows, owners, and intended control decisions. Evidence for aI use-case and dependency register concerns a different issue. The resource plan names owners and funded effort for each major AIMS activity, including post-launch monitoring.
D:A sample Annex A control has an auditable applicability rationale, associated risk treatment, owner, and current implementation status. Evidence for statement of Applicability creation concerns a different issue. The resource plan names owners and funded effort for each major AIMS activity, including post-launch monitoring.
Question 384
At Fictional Compass Logistics, the proposed AI governance implementation rollout is undergoing an ISO/IEC 42001 implementation review before a material expansion of AI use. The observed failure is: A deployment timeline allocates engineers for model launch but omits reviewers, operator training, logging, impact assessment, and recurring monitoring. A controlled correction and repeatable evidence are required before wider AIMS rollout. Which recurring safeguard best prevents this specific failure from recurring?
- For Fictional Compass Logistics under the scoped AI governance decision, reforecast staffing and budget at each stage gate and escalate material shortfalls.
- For Fictional Compass Logistics under the scoped AI governance decision, reassess harms after material data, audience, functionality, or jurisdiction changes.
- For Fictional Compass Logistics under the scoped AI governance decision, compare actual usage with forecasts and revise resource priorities as AIMS maturity grows.
- For Fictional Compass Logistics under the scoped AI governance decision, reassess gaps when scope, systems, or the selected standards baseline change.
Explanation
Correct Answer
C:Compare actual usage with forecasts and revise resource priorities as aIMS maturity grows. AIMS implementation resources extend beyond software build work to governance, human capability, measurement, and long-term maintenance. The resource plan names owners and funded effort for each major AIMS activity, including post-launch monitoring.
Incorrect Answers
A:Reforecast staffing and budget at each stage gate and escalate material shortfalls. Leadership resources and sponsorship is a separate risk. AIMS implementation resources extend beyond software build work to governance, human capability, measurement, and long-term maintenance. Compare actual usage with forecasts and revise resource priorities as aIMS maturity grows.
B:Reassess harms after material data, audience, functionality, or jurisdiction changes. AI risk assessment completeness is a separate risk. AIMS implementation resources extend beyond software build work to governance, human capability, measurement, and long-term maintenance. Compare actual usage with forecasts and revise resource priorities as aIMS maturity grows.
D:Reassess gaps when scope, systems, or the selected standards baseline change. Current-state AIMS gap analysis is a separate risk. AIMS implementation resources extend beyond software build work to governance, human capability, measurement, and long-term maintenance. Compare actual usage with forecasts and revise resource priorities as aIMS maturity grows.
Question 385
At Fictional Compass Logistics, the proposed AI governance implementation rollout is undergoing an ISO/IEC 42001 implementation review before a material expansion of AI use. The observed failure is: A deployment timeline allocates engineers for model launch but omits reviewers, operator training, logging, impact assessment, and recurring monitoring. A controlled correction and repeatable evidence are required before wider AIMS rollout. Which proposed shortcut must be REJECTED because it weakens reliability, correctness, auditability, or access control?
- For Fictional Compass Logistics under the scoped AI governance decision, estimate roles, skills, tools, evidence costs, and recurring operational capacity in a phased resource plan.
- For Fictional Compass Logistics under the scoped AI governance decision, the resource plan names owners and funded effort for each major AIMS activity, including post-launch monitoring.
- For Fictional Compass Logistics under the scoped AI governance decision, compare actual usage with forecasts and revise resource priorities as AIMS maturity grows.
- For Fictional Compass Logistics under the scoped AI governance decision, assume successful model deployment means the AIMS has no further recurring operating cost.
Explanation
Correct Answer
D:Do not assume successful model deployment means the AIMS has no further recurring operating cost. AIMS implementation resources extend beyond software build work to governance, human capability, measurement, and long-term maintenance. Estimate roles, skills, tools, evidence costs, and recurring operational capacity in a phased resource plan. The resource plan names owners and funded effort for each major AIMS activity, including post-launch monitoring.
Incorrect Answers
A:Estimate roles, skills, tools, evidence costs, and recurring operational capacity in a phased resource plan. This is the controlled remediation, not the unsafe shortcut. It addresses AIMS implementation resources extend beyond software build work to governance, human capability, measurement, and long-term maintenance. The unsafe step is to assume successful model deployment means the AIMS has no further recurring operating cost.
B:The resource plan names owners and funded effort for each major AIMS activity, including post-launch monitoring. This is measurable acceptance evidence rather than a risky change. It provides evidence that the scoped remediation was successful: Estimate roles, skills, tools, evidence costs, and recurring operational capacity in a phased resource plan. The unsafe step is to assume successful model deployment means the AIMS has no further recurring operating cost.
C:Compare actual usage with forecasts and revise resource priorities as aIMS maturity grows. This is a preventive operational safeguard that reduces recurrence because aIMS implementation resources extend beyond software build work to governance, human capability, measurement, and long-term maintenance. It should be retained. The unsafe proposal is assume successful model deployment means the AIMS has no further recurring operating cost.
Question 386
At Fictional Glacier Manufacturing, the ISO/IEC 42001 implementation planning program is undergoing an ISO/IEC 42001 implementation review after an internal audit finding. The observed failure is: A deployment timeline allocates engineers for model launch but omits reviewers, operator training, logging, impact assessment, and recurring monitoring. The implementation may continue only after measurable evidence demonstrates the intended control outcome. Which scoped implementation action should the AIMS lead take first?
- For Fictional Glacier Manufacturing while preserving approved oversight, define in-scope organizational entities and shared AI interfaces, plus responsibilities and control arrangements for services crossing the boundary.
- For Fictional Glacier Manufacturing while preserving approved oversight, build a RACI-style responsibility map with a single accountable approval authority and documented consultation and escalation paths.
- For Fictional Glacier Manufacturing while preserving approved oversight, estimate roles, skills, tools, evidence costs, and recurring operational capacity in a phased resource plan.
- For Fictional Glacier Manufacturing while preserving approved oversight, obtain a current obligation map by jurisdiction and use case, assign owners, and embed required controls in the AIMS plan.
Explanation
Correct Answer
C:Estimate roles, skills, tools, evidence costs, and recurring operational capacity in a phased resource plan. AIMS implementation resources extend beyond software build work to governance, human capability, measurement, and long-term maintenance. The resource plan names owners and funded effort for each major AIMS activity, including post-launch monitoring.
Incorrect Answers
A:Define in-scope organizational entities and shared AI interfaces, plus responsibilities and control arrangements for services crossing the boundary. A management-system scope should describe real organizational boundaries and shared processes to avoid accountability gaps at interfaces. A deployment timeline allocates engineers for model launch but omits reviewers, operator training, logging, impact assessment, and recurring monitoring. Estimate roles, skills, tools, evidence costs, and recurring operational capacity in a phased resource plan.
B:Build a RACI-style responsibility map with a single accountable approval authority and documented consultation and escalation paths. Diffuse accountability creates control gaps unless responsibilities and approval rights are unambiguous for each decision. A deployment timeline allocates engineers for model launch but omits reviewers, operator training, logging, impact assessment, and recurring monitoring. Estimate roles, skills, tools, evidence costs, and recurring operational capacity in a phased resource plan.
D:Obtain a current obligation map by jurisdiction and use case, assign owners, and embed required controls in the AIMS plan. Risk treatment cannot demonstrate conformity when legal and contractual requirements for the use context are unknown or outdated. A deployment timeline allocates engineers for model launch but omits reviewers, operator training, logging, impact assessment, and recurring monitoring. Estimate roles, skills, tools, evidence costs, and recurring operational capacity in a phased resource plan.
Question 387
At Fictional Glacier Manufacturing, the ISO/IEC 42001 implementation planning program is undergoing an ISO/IEC 42001 implementation review after an internal audit finding. The observed failure is: A deployment timeline allocates engineers for model launch but omits reviewers, operator training, logging, impact assessment, and recurring monitoring. The implementation may continue only after measurable evidence demonstrates the intended control outcome. Which underlying mechanism best explains these symptoms?
- For Fictional Glacier Manufacturing while preserving approved oversight, AI risk assessments should address relevant harms and opportunities in context rather than equating all AI risk with information security.
- For Fictional Glacier Manufacturing while preserving approved oversight, AIMS implementation resources extend beyond software build work to governance, human capability, measurement, and long-term maintenance.
- For Fictional Glacier Manufacturing while preserving approved oversight, a management-system scope should describe real organizational boundaries and shared processes to avoid accountability gaps at interfaces.
- For Fictional Glacier Manufacturing while preserving approved oversight, a governance implementation program needs an explicit charter so stakeholders can distinguish authorized scope and success criteria from unbounded aspirations.
Explanation
Correct Answer
B:AIMS implementation resources extend beyond software build work to governance, human capability, measurement, and long-term maintenance. Estimate roles, skills, tools, evidence costs, and recurring operational capacity in a phased resource plan. The resource plan names owners and funded effort for each major AIMS activity, including post-launch monitoring.
Incorrect Answers
A:AI risk assessments should address relevant harms and opportunities in context rather than equating all AI risk with information security. A deployment timeline allocates engineers for model launch but omits reviewers, operator training, logging, impact assessment, and recurring monitoring. AIMS implementation resources extend beyond software build work to governance, human capability, measurement, and long-term maintenance.
C:A management-system scope should describe real organizational boundaries and shared processes to avoid accountability gaps at interfaces. A deployment timeline allocates engineers for model launch but omits reviewers, operator training, logging, impact assessment, and recurring monitoring. AIMS implementation resources extend beyond software build work to governance, human capability, measurement, and long-term maintenance.
D:A governance implementation program needs an explicit charter so stakeholders can distinguish authorized scope and success criteria from unbounded aspirations. A deployment timeline allocates engineers for model launch but omits reviewers, operator training, logging, impact assessment, and recurring monitoring. AIMS implementation resources extend beyond software build work to governance, human capability, measurement, and long-term maintenance.
Question 388
At Fictional Glacier Manufacturing, the ISO/IEC 42001 implementation planning program is undergoing an ISO/IEC 42001 implementation review after an internal audit finding. The observed failure is: A deployment timeline allocates engineers for model launch but omits reviewers, operator training, logging, impact assessment, and recurring monitoring. The implementation may continue only after measurable evidence demonstrates the intended control outcome. Which observable acceptance test most directly shows that this defect is fixed?
- For Fictional Glacier Manufacturing while preserving approved oversight, the resource plan names owners and funded effort for each major AIMS activity, including post-launch monitoring.
- For Fictional Glacier Manufacturing while preserving approved oversight, a chosen use case traces from its business purpose to supplier dependencies, data flows, owners, and intended control decisions.
- For Fictional Glacier Manufacturing while preserving approved oversight, the signed charter names accountable sponsors, major deliverables, approved resources, and criteria for moving between phases.
- For Fictional Glacier Manufacturing while preserving approved oversight, the pilot produces signed acceptance evidence and region-specific obligations that inform the authorized subsequent rollout.
Explanation
Correct Answer
A:The resource plan names owners and funded effort for each major AIMS activity, including post-launch monitoring. AIMS implementation resources extend beyond software build work to governance, human capability, measurement, and long-term maintenance. Estimate roles, skills, tools, evidence costs, and recurring operational capacity in a phased resource plan.
Incorrect Answers
B:A chosen use case traces from its business purpose to supplier dependencies, data flows, owners, and intended control decisions. Evidence for aI use-case and dependency register concerns a different issue. The resource plan names owners and funded effort for each major AIMS activity, including post-launch monitoring.
C:The signed charter names accountable sponsors, major deliverables, approved resources, and criteria for moving between phases. Evidence for aIMS implementation charter concerns a different issue. The resource plan names owners and funded effort for each major AIMS activity, including post-launch monitoring.
D:The pilot produces signed acceptance evidence and region-specific obligations that inform the authorized subsequent rollout. Evidence for multi-site phased rollout concerns a different issue. The resource plan names owners and funded effort for each major AIMS activity, including post-launch monitoring.
Question 389
At Fictional Glacier Manufacturing, the ISO/IEC 42001 implementation planning program is undergoing an ISO/IEC 42001 implementation review after an internal audit finding. The observed failure is: A deployment timeline allocates engineers for model launch but omits reviewers, operator training, logging, impact assessment, and recurring monitoring. The implementation may continue only after measurable evidence demonstrates the intended control outcome. Which recurring safeguard best prevents this specific failure from recurring?
- For Fictional Glacier Manufacturing while preserving approved oversight, calibrate risk criteria and assessor guidance as evidence and risk appetite change.
- For Fictional Glacier Manufacturing while preserving approved oversight, compare actual usage with forecasts and revise resource priorities as AIMS maturity grows.
- For Fictional Glacier Manufacturing while preserving approved oversight, review objective relevance and measured outcomes during implementation steering meetings.
- For Fictional Glacier Manufacturing while preserving approved oversight, exercise important supplier continuity paths and review contract terms after service changes.
Explanation
Correct Answer
B:Compare actual usage with forecasts and revise resource priorities as aIMS maturity grows. AIMS implementation resources extend beyond software build work to governance, human capability, measurement, and long-term maintenance. The resource plan names owners and funded effort for each major AIMS activity, including post-launch monitoring.
Incorrect Answers
A:Calibrate risk criteria and assessor guidance as evidence and risk appetite change. Risk criteria before assessment is a separate risk. AIMS implementation resources extend beyond software build work to governance, human capability, measurement, and long-term maintenance. Compare actual usage with forecasts and revise resource priorities as aIMS maturity grows.
C:Review objective relevance and measured outcomes during implementation steering meetings. Measurable AIMS objective setting is a separate risk. AIMS implementation resources extend beyond software build work to governance, human capability, measurement, and long-term maintenance. Compare actual usage with forecasts and revise resource priorities as aIMS maturity grows.
D:Exercise important supplier continuity paths and review contract terms after service changes. Cloud AI supplier dependency planning is a separate risk. AIMS implementation resources extend beyond software build work to governance, human capability, measurement, and long-term maintenance. Compare actual usage with forecasts and revise resource priorities as aIMS maturity grows.
Question 390
At Fictional Glacier Manufacturing, the ISO/IEC 42001 implementation planning program is undergoing an ISO/IEC 42001 implementation review after an internal audit finding. The observed failure is: A deployment timeline allocates engineers for model launch but omits reviewers, operator training, logging, impact assessment, and recurring monitoring. The implementation may continue only after measurable evidence demonstrates the intended control outcome. Which proposed shortcut must be REJECTED because it weakens reliability, correctness, auditability, or access control?
- For Fictional Glacier Manufacturing while preserving approved oversight, estimate roles, skills, tools, evidence costs, and recurring operational capacity in a phased resource plan.
- For Fictional Glacier Manufacturing while preserving approved oversight, assume successful model deployment means the AIMS has no further recurring operating cost.
- For Fictional Glacier Manufacturing while preserving approved oversight, the resource plan names owners and funded effort for each major AIMS activity, including post-launch monitoring.
- For Fictional Glacier Manufacturing while preserving approved oversight, compare actual usage with forecasts and revise resource priorities as AIMS maturity grows.
Explanation
Correct Answer
B:Do not assume successful model deployment means the AIMS has no further recurring operating cost. AIMS implementation resources extend beyond software build work to governance, human capability, measurement, and long-term maintenance. Estimate roles, skills, tools, evidence costs, and recurring operational capacity in a phased resource plan. The resource plan names owners and funded effort for each major AIMS activity, including post-launch monitoring.
Incorrect Answers
A:Estimate roles, skills, tools, evidence costs, and recurring operational capacity in a phased resource plan. This is the controlled remediation, not the unsafe shortcut. It addresses AIMS implementation resources extend beyond software build work to governance, human capability, measurement, and long-term maintenance. The unsafe step is to assume successful model deployment means the AIMS has no further recurring operating cost.
C:The resource plan names owners and funded effort for each major AIMS activity, including post-launch monitoring. This is measurable acceptance evidence rather than a risky change. It provides evidence that the scoped remediation was successful: Estimate roles, skills, tools, evidence costs, and recurring operational capacity in a phased resource plan. The unsafe step is to assume successful model deployment means the AIMS has no further recurring operating cost.
D:Compare actual usage with forecasts and revise resource priorities as aIMS maturity grows. This is a preventive operational safeguard that reduces recurrence because aIMS implementation resources extend beyond software build work to governance, human capability, measurement, and long-term maintenance. It should be retained. The unsafe proposal is assume successful model deployment means the AIMS has no further recurring operating cost.